REPORT/RECOMMENDATION TO THE BOARD OF DIRECTORS
OF THE BIG BEAR VALLEY RECREATION AND PARK DISTRICT
AND RECORD OF ACTION
March 24, 2020
FROM
LUTHER SNOKE, Interim Director, Special Districts Department
SUBJECT
Title
Construction Contract Revisions for the Big Bear Alpine Zoo Relocation Project
End
RECOMMENDATION(S)
Recommendation
Acting as the governing body of the Big Bear Valley Recreation and Park District:
1. Approve Amendment No. 4 to Contract No. 16-258 with M.S. Construction Management Group (MSCMG) in the amount of $322,734.60 (increasing the total contract amount from $9,985,138.52 to $10,307,873.12) for required and agreed upon changes to facilitate completion of the Big Bear Alpine Zoo Relocation Project (Project).
2. Approve Change Order No. 6 Contract No. 16-258 with MSCMG in the amount of $52,202.64 (increasing the total contract amount from $10,307,873.12 to $10,360,075.76) for required and agreed upon changes to facilitate Project completion (Four votes required).
(Presenter: Luther Snoke, Interim Director, 386-8811)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The combined cost of $374,937.24 for the recommended adjustments to Contract No. 16-258 will be funded through the Project’s construction and contingency budget without the need for additional funding.
The Project’s current projected cost of $18.2 million, which includes these recommended contract increases, is funded through various sources including a $5.5 million loan from the County General Fund to the Big Bear Valley Recreation and Park District (BBVRPD) as approved by the Board of Directors (Board) on October 8, 2019 (Item No. 58).
BACKGROUND INFORMATION
BBVRPD operates the Big Bear Alpine Zoo (Zoo). The current facility, which is located in the Moonridge area of Big Bear, is small and outdated making it difficult to care properly for the animals. In 2010, BBVRPD purchased property to relocate and expand the Zoo. At that time, BBVRPD also began working on conceptual plans for this new site.
On May 24, 2016 (Item No. 197), the Board awarded a construction contract in the amount of $8,544,000 to MSCMG to build the new Zoo facility. The notice to proceed for construction was issued on June 15, 2016 but was later changed to July 5, 2016. The following are changes that have occurred to this contract:
• On September 27, 2016, the Director of Special Districts, as authorized by the Board pursuant to Public Contract Code section 20142, approved an administrative change order (Change Order No. 1) to MSCMG to add $48,589.63 to the contract amount and 7 days to the contract time to address excessive, oversaturated soil conditions that caused the need for additional excavation, and rock stabilization under building foundations. This action increased the contract amount from $8,544,000 to $8,592,589.63.
• On January 23, 2018 (Item No. 54), BBVRPD and MSCMG mutually agreed to Contract Amendment No. 1, increasing the contract amount by $150,000 and extending the contract time to December 30, 2018 for construction of the Grizzly Stream feature in the Grizzly Bear enclosure, which was funded by donations. This action increased the contract amount from $8,592,589.63 to $8,742,589.63.
• On November 19, 2018, the Director of Special Districts, as authorized by the Board pursuant to Public Contract Code section 20142, approved an administrative change order (Change Order No. 2) to MSCMG in the amount of $106,103.59 to address plan conflicts, code requirements, and constructability issues. This action increased the contract amount from $8,742,589.63 to $8,848,693.22.
• On October 8, 2019 (Item No. 58), BBVRPD and MSCMG mutually agreed to Contract Amendment No. 2, increasing the contract amount by $604,824.26 and extending the contract time to June 25, 2019 for various items such as additional storm drain lines, animal caging modifications, and anti-dig barriers. Additionally, on October 8, 2019 (Item No. 58), the Board approved Change Order No. 3 to increase the contract amount by $56,779.47 and extending the contract time to July 1, 2019 for various items such as building modifications and animal caging modifications. These two actions increased the contract amount from $8,848,693.22 to $9,510,296.95.
• On December 17, 2019 (Item No. 68), BBVRPD and MSCMG mutually agreed to Contract Amendment No. 3, increasing the contract amount by $97,500.26 and extending the contract time to December 21, 2019 for general conditions related to the time extension. Additionally, on December 17, 2019 (Item No. 68), the Board approved Change Order No. 4 increasing the contract amount by $83,517.14 and extending the contract time to December 24, 2019 for various items such as building modifications and animal caging modifications. Furthermore, on December 17, 2019 (Item No. 68), the Board approved Construction Change Directive (CCD)-Change Order No. 5 increasing the contract amount by $293,824.17 for various items such as fencing modifications, viewing area changes, and building modifications. These three actions increased the contract amount from $9,510,296.95 to $9,985,138.52.
The recommended Amendment No. 4 to Contract No. 16-258 compensates MSCMG in the amount of $322,734.60 for the cost of laminated exhibit glazing upsizing for black bear and grizzly viewing areas, additional asphalt paving and retaining wall near Building 60, modifications to drainage for storm drain bioswale, and ribbon gutter revisions. Board approval of Amendment No. 4 will increase the contract amount from $9,985,138.52 to $10,307,873.12.
The recommended Change Order No. 6 to Contract No. 16-258 compensates MSCMG in the amount of $52,202.64 for the cost of fencing modifications to add additional height to the south Black Bear exhibit for animal and visitor safety. Board approval of Change Order No. 4 will increase the contract amount from $10,307,873.12 to $10,360,075.76.
There are additional contract changes under negotiation for both compensation and contract time that will be submitted for Board approval in a future agenda item(s). The Project’s current projected cost of $18.2 million includes a project contingency. It is expected that the future contract changes will be funded from this contingency.
PROCUREMENT
MSCMG was awarded this construction contract after the Special Districts Department conducted a competitive bid process. The additional cost items in Amendment No. 4 and Change Order No. 6 are related to events that took place after the competitive bid processes. Therefore, no additional procurement activities are required.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Sophie Akins, Deputy County Counsel, 387-5455) on March 4, 2020; Finance (Tom Forster, Administrative Analyst, 387-4635) on March 6, 2020; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on March 9, 2020.