Subject: Amendment to Contracts for Plan Review, Inspection, Emergency Response, and Special Projects
Attachments: 1. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - West Coast Code Consultants, Inc., 2. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - Hayer Consultants Inc, 3. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - Jason Addison Smith Consulting Services, Inc. dba JAS Pacific, 4. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - NV5 INC, 5. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - TRB and Associates, Inc., 6. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - Willdan Engineering Inc., 7. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - 4LEAF, Inc., 8. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - Bureau Veritas North America, Inc., 9. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - CSG Consultants, Inc, 10. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - Interwest Consulting Group, Inc., 11. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - JLEE Engineering, Inc., 12. ADD-CON-LUS-08-06-2024-BNS Amendment No. 3 - Transtech Engineers, Inc., 13. Item #25 Executed BAI, 14. 21-589 A-3 Executed Contract, 15. 21-590 A-3 Executed Contract, 16. 21-591 A-3 Executed Contract, 17. 21-592 A-3 Executed Contract, 18. 21-593 A-3 Executed Contract, 19. 21-594 A-3 Executed Contract, 20. 21-595 A-3 Executed Contract, 21. 21-596 A-3 Executed Contract, 22. 21-597 A-3 Executed Contract, 23. 21-598 A-3 Execeuted Contract, 24. 21-587 A-3 Executed Contract, 25. 21-588 A-3 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

August 6, 2024

FROM
MARK WARDLAW, Director, Land Use Services Department

SUBJECT
Title
Amendment to Contracts for Plan Review, Inspection, Emergency Response, and Special Projects
End

RECOMMENDATION(S)
Recommendation
Approve Amendment No. 3 to the following contracts, for the provision of on-call Building and Safety plan review, permit inspection, emergency response, and special projects services, extending the term for one additional year, for the total contract period of August 13, 2021, through August 12, 2025, with no change to the total not-to-exceed aggregate amount of $12,750,000:
1. 4LEAF, Inc. Contract No. 21-587
2. Bureau Veritas North America, Inc., Contract No. 21-588
3. CSG Consultants, Inc., Contract No. 21-589
4. Hayer Consultants, Inc., Contract No. 21-590
5. Interwest Consulting Group, Inc., Contract No. 21-591
6. Jason Addison Smith Consulting Services, Inc. dba JAS Pacific, Contract No. 21-592
7. J LEE Engineering, Inc., Contract No. 21-593
8. NV5, Inc., Contract No. 21-594
9. TRANSTECH Engineers, Inc., Contract No. 21-595
10. TRB and Associates, Inc., Contract No. 21-596
11. West Coast Code Consultants, Inc., Contract No. 21-597
12. Willdan Engineering Inc., Contract No. 21-598
(Presenter: Mark Wardlaw, Director, 387-4431)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this Amendment will not result in the use of additional Discretionary General Funding (Net County Cost). There will be no increase to the not-to-exceed total aggregate amount of $12,750,000. Sufficient appropriation is included in the Land Use Services (LUS) Building and Safety (BNS) Division 2024-25 b...