REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
August 20, 2024
FROM
DON DAY, Director, Project and Facilities Management Department
SUBJECT
Title
Net Energy Metering and Renewable Electrical Generating Facility Interconnection Agreement with Southern California Edison Company
End
RECOMMENDATION(S)
Recommendation
Approve non-financial Net Energy Metering and Renewable Electrical Generating Facility Interconnection Agreement, including non-standard terms, with Southern California Edison Company for the Energy Efficiency Solutions Project, continuing perpetually until terminated by either party.
(Presenter: Don Day, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.
FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Fund (Net County Cost) as the Southern California Edison Company Net Energy Metering (NEM) and Renewable Electrical Generating Facility Interconnection Agreement (Agreement) is non-financial in nature.
BACKGROUND INFORMATION
On October 24, 2023 (Item No. 90), the Board of Supervisors (Board) approved the Energy Efficiency Solutions Project (Project) (WBSE 10.10.1566). This ongoing construction initiative aims to align with California's state-wide sustainability efforts by installing energy-efficient measures, including lighting, heating, ventilation, air-conditioning system controls, and solar photovoltaic (PV) energy systems. The Project consists of various energy-efficient improvements at County-owned facilities located at 385 North Arrowhead Avenue and 268 West Hospitality Lane (268 Hospitality) in San Bernardino. The improvements to 268 Hospitality include the installation of a 500-kilowatt solar carport system with a battery energy storage syste...
Click here for full text