Subject: Project Baseline Agreement with the San Bernardino County Transportation Authority for Trade Corridor Enhancement Program Funds for the Baker Boulevard Bridge Replacement Project Over the Mojave River in the Unincorporated Community of Baker
Attachments: 1. CON-PW-Trans 1-13-26 Project Baseline Agreement with CTC and SBCTA Baker Blvd Bridge (ADG_Signed), 2. COV-PW-Trans 1-13-26 Project Baseline Agreement with CTC and SBCTA Baker Blvd Bridge, 3. MAP-PW-Trans 1-13-26 Project Baseline Agreement with CTC and SBCTA Baker Blvd Bridge
Date Action ByActionResultAction DetailsAgenda DocumentsVideo
No records to display.
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

January 13, 2026
FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation

SUBJECT
Title
Project Baseline Agreement with the San Bernardino County Transportation Authority for Trade Corridor Enhancement Program Funds for the Baker Boulevard Bridge Replacement Project Over the Mojave River in the Unincorporated Community of Baker
End

RECOMMENDATION(S)
Recommendation
Approve Project Baseline Agreement with the San Bernardino County Transportation Authority and the California Transportation Commission, for the Baker Boulevard Bridge Replacement Project over the Mojave River, in the amount of $18,369,000, in Trade Corridor Enhancement Program funds and $11,426,000 of Measure I Major Local Highways Program and Surface Transportation Program funds, for a total Project cost of $29,975,000, effective upon execution by all parties through April 30, 2030.
(Presenter: Byanka Velasco, Assistant Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The estimated total cost of the Baker Boulevard Bridge Replacement Project over the Mojave River (Project) is $29,795,000. This cost will be funded by the Trade Corridor Enhancement Program (TCEP), in the amount of $18,369,000 allocated by the California Transportation Commission (CTC) and Measure I Major Local Highways Program (MLHP) and Surface Transportation Program (STP), in the amount of $11,426,000, administered by the San Bernardino County Transportation Authority (SBCTA). The Department of Public Works (Department) will return to the Board of Supervisors (Board) to request any necessary budget adjustments conc...