Legislation Details

File #: 15198   
Type: Consent Status: Agenda Ready
File created: 11/5/2026 Department: Airports
On agenda: 11/17/2026 Final action:
Subject: Annual Report of Federal Aviation Administration Airport Improvement Program Grant Agreements Executed Under Delegated Authority
Date Action ByActionResultAction DetailsAgenda DocumentsVideo
No records to display.

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

                                          November 17, 2026

 

FROM

BRETT J. GODOWN, DIRECTOR, Department of Airports 

         

SUBJECT                      

Title                     

Annual Report of Federal Aviation Administration Airport Improvement Program Grant Agreements Executed Under Delegated Authority

End

 

RECOMMENDATION(S)

Recommendation

Receive an annual report of Federal Aviation Administration Airport Improvement Program Grant Agreements for certain airport capital improvement projects executed by the Director of Airports pursuant to delegated authority for the period ending September 30, 2026.

(Presenter: Brett J. Godown, Director, 387-8810)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Operate in a Fiscally-Responsible and Business-Like Manner.

 

FINANCIAL IMPACT

Receipt of this item will not require the use of Discretionary General Funding (Net County Cost). The Federal Aviation Administration (FAA) Airport Improvement Program Grant Agreements executed under delegated authority awarded a total of $8,189,417 for the Airport Capital Improvement Plan (ACIP) projects listed below:

 

Airport

ACIP Project

FAA Grant Award

Apple Valley Airport

26-1 Reconstruct Vault Building and Equipment (Design)

$164,732

Apple Valley Airport

27-1 Apple Valley Airport Rehabilitate Runway 18/36

$5,936,870

Twentynine Palms Airport

26-1 Reconstruct Airfield Drainage (Phase II Construction)

$2,087,815

Total

$8,189,417

 

Sufficient appropriation and revenue have been included in the Airports 2026-2027 budget and will be included in future recommended budgets, if necessary.

 

BACKGROUND INFORMATION

On December 16, 2025 (Item No. 132), the Board of Supervisors (Board), acting on behalf of San Bernardino County (County) and County Service Area 60- Apple Valley Airport (CSA-60), received a list of anticipated ACIP projects for the period of October 1, 2026 through September 30, 2031 at eligible airports managed by the Department of Airports (Airports). The Board also delegated authority to the Director of Airports for the period of December 16, 2025 through December 15, 2026, to execute and submit FAA standard forms of pre-applications, applications, fund transfer requests, and award agreements for ACIP projects, in an amount, per ACIP project, not to exceed the total estimated funding from the FAA per ACIP project as set forth in the ACIP list received by the Board plus a fifteen percent contingency, subject to County Counsel review. As part of that action, the Board directed the department to provide an annual report to the Board of all FAA grant agreements for ACIP projects executed by the Director of Airports under this delegated authority for the period ending September 30, 2026.

 

The ACIP list received by the Board included ACIP Project 26-1 at Twentynine Palms. Due to an expanded project scope, the department returned to the Board on February 10, 2026 (Item No. 3), for delegated authority for the Director of Airports to: (a) execute and submit FAA standard forms of pre-applications, applications, fund transfer requests, and award agreements for the Twentynine Palms project for an increased amount of $3,045,700, rather than the original amount, including contingency of $1,092,500, and (b) execute and submit California Department of Transportation (Caltrans) standard forms of application, award agreements, and non-substantive documents for a matching grant in an amount of $152,285.

 

For the period ending September 30, 2026, the Director of Airports executed the following FAA Airport Improvement Program Grant Agreements to accept a total of $8,189,417 in FAA grant funds, with grant awards below the delegated authority amount due to refinement of project specifications, receipt of bids, or other adjustments:

 

FAA Grant Agreement No.

ACIP Project

Delegated Authority Amount

FAA Grant Award

Department Director Execution Date

3-06-0009-013-2026

APV 26-1 Reconstruct Vault Building and Equipment (Design)

$332,500

$164,732

07/13/2026

3-06-0009-014-2026

APV 27-1 Rehabilitate Runway 18/36

$8,309,937

$5,936,870

09/01/2026

3-06-0267-011-2026

TNP 26-1 Reconstruct Airfield Drainage (Phase II Construction)

$3,045,700

$2,087,815

07/22/2026

Total FAA Grant Awards

 

$8,189,417

 

 

The FAA funds provided under the grant agreements must be used within four years of the County’s acceptance. FAA awards are based on updated budgeted costs for the ACIP projects, and because additional funds are available, the grants cover approximately 95% of the project cost. Airports and anticipated Caltrans Matching Grants will fund the remaining 5%.

 

PROCUREMENT

N/A

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Agnes Cheng, Deputy County Counsel, 909-387-5455) on October 23, 2026; and County Finance and Administration (Elisbeth Castaneda, Administrative Analyst, 387-5109) on October 27, 2026.