San Bernardino header
File #: 10424   
Type: Consent Status: Passed
File created: 6/26/2024 Department: Multijurisdictional Items
On agenda: 7/9/2024 Final action: 7/9/2024
Subject: Various Actions Regarding the County Service Area 42 Oro Grande - Oro Grande Park Revitalization Phase 2 Project
Attachments: 1. CON-MULTI-070924 CSA 42 Oro Grande Park Revitalization Project Contract Award, 2. ATT-MULTI-070924 CSA 42 Oro Grande Park Revitalization Project Addendum No.1, 3. Item #67 Executed BAI, 4. 24-627 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE FOLLOWING:
SAN BERNARDINO COUNTY
BOARD GOVERNED COUNTY SERVICE AREAS
AND RECORD OF ACTION

July 9, 2024

FROM
NOEL CASTILLO, Director, Department of Public Works - Special Districts
LUTHER SNOKE, Chief Executive Office, County Administrative Office

SUBJECT
Title
Various Actions Regarding the County Service Area 42 Oro Grande - Oro Grande Park Revitalization Phase 2 Project
End

RECOMMENDATION(S)
Recommendation
1. Acting as the governing body of County Service Area 42 Oro Grande:
a. Approve a 2024-25 budget increase of $342,029, from $888,811 to $1,230,840, for the County Service Area 42 Oro Grande - Oro Grande Park Revitalization Phase 2 Project.
b. Authorize the Auditor-Controller/Treasurer/Tax Collector to post budget adjustments, as detailed in the Financial Impact section, for the County Service Area 42 Oro Grande - Oro Grande Park Revitalization Phase 2 Project (Four votes required).
c. Approve Addendum No. 1, issued on May 1, 2024, to the bid documents for the County Service Area 42 Oro Grande - Oro Grande Park Revitalization Phase 2 Project.
d. Award construction contract to C.S. Legacy Construction, Inc. (Walnut, CA) in the amount of $874,878.93 for the County Service Area 42 Oro Grande - Oro Grande Park Revitalization Phase 2 Project.
e. Authorize the Director of the Department of Public Works to approve necessary changes or additions in the work being performed under the construction contract with C.S. Legacy Construction, Inc., for a total amount not-to-exceed $56,243.95, pursuant to Public Contract Code Section 20142.
f. Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.
2. Acting as the governing body of San Bernardino County, approve an increase of $267,029, from $888,811 to $1,155,840, of American Rescue Plan Act funding for eligible costs associated with the County Service Area 42 Oro...

Click here for full text