REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
May 6, 2025
FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation
SUBJECT
Title
Cooperative Agreements with the City of San Bernardino for Pavement Improvement and Americans with Disabilities Act Curb Ramp Projects in the San Bernardino Area
End
RECOMMENDATION(S)
Recommendation
1. Approve the termination of Cooperative Agreement No. 21-782 with the City of San Bernardino, for pavement and Americans with Disabilities Act curb ramp improvements on various roads in the San Bernardino area.
2. Approve the following Cooperative Agreements with the City of San Bernardino, for the following pavement and Americans with Disabilities Act curb ramp improvement projects:
a. Cooperative Agreement for the Muscoy Area Rehabilitation - Phase I Project, wherein the County will contribute an estimated amount of $3,519,000, and the City of San Bernardino will contribute an estimated amount of $375,000, towards the estimated total cost of $3,894,000, effective May 6, 2025 through April 30, 2030, or until the project is completed and final payment is made, whichever comes first.
b. Cooperative Agreement for the Lynwood Drive and Other Roads Pavement Improvement Project, wherein the County will contribute an estimated amount of $7,110,000, and the City of San Bernardino will contribute an estimated amount of $1,730,000, towards the estimated total cost of $8,840,000, effective May 6, 2025 through April 30, 2030, or until the project is completed and final payment is made, whichever comes first.
c. Cooperative Agreement for the Citrus Street and Other Roads - Phase I Pavement Improvement Project, wherein the County will contribute an estimated amount of $5,724,000, and the City of San Bernardino will contribute an estimated amount of $239,000, towards the estimated total cost of $5,963,000, effective May 6, 2025 through April 30, 2030, or until the project i...
Click here for full text