REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
April 7, 2026
FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation
SUBJECT
Title
Amendment to Cooperative Agreement with San Bernardino County Transportation Authority for the Cedar Avenue at Interstate 10 Interchange Project in the Bloomington Area
End
RECOMMENDATION(S)
Recommendation
Approve Amendment No. 2 to Cooperative Agreement No. 18-865 (Funding Agreement 18-1001962) with the San Bernardino County Transportation Authority for Right-of-Way and Construction of the Cedar Avenue at Interstate 10 Interchange Project in the Bloomington area, to adjust the parties funding responsibilities based on the revised project costs, increasing the total project cost by $20,504,000, from $113,393,000 to $133,897,000, update the project milestone dates and extend the term by five years, for a new term of January 9, 2019 to December 31, 2033.
(Presenter: David Doublet, Assistant Director, 386-8811)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Promote and Fulfill the Countywide Vision.
Foster Sustainable Development Through Strategic Partnerships.
FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The Cedar Avenue at Interstate 10 (I-10) Interchange Project in the Bloomington area (Project) estimated total cost increased by $20,504,000. In accordance with the San Bernardino County Transportation Authority (SBCTA) Measure I 2010-2040 Expenditure Plan and Nexus Study, SBCTA's Public Share of the increase will be $10,782,800, the Project will receive $5,000,000 from the Section 190 Grade Separation Program, and the remaining $4,721,200 will be the Local Agency Share (Developer Share).
The Developer Share will be divided between the County, the City of Rialto (Rialto), and the City of Fontana (Fontana) (collectively, Cities), based on the spec...