REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF SAN BERNARDINO COUNTY

AND RECORD OF ACTION

 

July 25, 2023

 

FROM

BRENDON BIGGS, Director, Department of Public Works - Transportation

 

SUBJECT

Title

Contract with All American Asphalt for the Park Drive and Other Roads Project in the Wrightwood

Area

End

 

RECOMMENDATION(S)

Recommendation

1.                     Award a construction contract to All American Asphalt (Corona, CA), in the amount of $829,819 for the Park Drive and Other Roads Project in the Wrightwood area.

2.                     Authorize a contingency fund of $82,981 for the Park Drive and Other Roads Project in the Wrightwood area.

3.                     Authorize the Director of the Department of Public Works to approve the expenditure of the contingency fund of $82,981 for verified quantity overruns for this unit priced construction contract.

4.                     Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the contract for a total amount not-to-exceed $53,990 of the $82,981 contingency fund, pursuant to Public Contract Code section 20142.

5.                     Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.

(Presenter: Brendon Biggs, Director, 387-7906)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Park Drive and Other Roads Project in the Wrightwood area (Project) will be funded with Senate Bill 1 (SB 1) Road Maintenance and Rehabilitation Account (RMRA) funds. Sufficient appropriation and revenue are included in the Department of Public Works (Department) 2023-24 Road Operations budget (66500002000 34H15113) and will be included in future recommended budgets.

 

BACKGROUND INFORMATION

The Project involves approximately 0.35 miles of pavement rehabilitation and reconstruction on Park Drive, pavement rehabilitation on Apple Avenue and Evergreen Road, constructing new curb ramps in accordance with current design standards and pursuant to the Americans with Disabilities Act (ADA) guidelines, constructing sidewalks, curb and gutters at various locations, and constructing a new concrete drainage swale.  Minimal work for the Project will be done outside of existing right-of-way and will require permission from property owners; however, no acquisitions will be required.  

 

The Project was prioritized by the Board of Supervisors (Board) as part of the 2019-20 SB 1 RMRA project list approved on April 21, 2020 (Item No. 45). Updating of existing or installation of new ADA compliant curb ramps in the Project area are required for the subject road improvements under the federal 2013 Department of Justice/Department of Transportation Joint Technical Assistance on the Title II of the ADA Requirements to Provide Curb Ramps when Streets, Roads, or Highways are Altered through Resurfacing guidelines.

 

On January 10, 2023 (Item No. 37), the Board determined the Project was exempt under the California Environmental Quality Act, approved the Project as defined in the Notice of Exemption, and directed the Clerk of the Board to file and post said notice.

 

The Project aligns with the County and the Chief Executive Officer’s goals and objectives of ensuring development of a well-planned, balanced and sustainable County by preserving and improving the structural integrity of existing road surfaces and access for pedestrians, including those with disabilities.

 

Upon Board approval of this item, construction is anticipated to commence end of August 2023 and be completed by the beginning of October 2023.

 

PROCUREMENT

On May 9, 2023 (Item No. 40), the Board approved the Project’s plans and specifications, as well as authorized the Director of the Department to advertise the Project for bids.  This Project was advertised in the Daily Press and in the Precinct Reporter on June 1, 2023 and released on the County Electronic Procurement Network (ePro) on May 30, 2023.  Notice inviting bids was also provided to specified construction trade journals as required by Public Contract Code section 22036. On June 22, 2023, the following three bids were received:

 

Contractor

Location

Total Bid

All American Asphalt

Corona, CA

$829,819.00

Hardy & Harper, Inc.

Lake Forest, CA

$870,000.00

Onyx Paving Company

Anaheim, CA

$1,230,100.00

 

The Department has reviewed the bids received and determined that they are responsive and recommends entering into a contract with All American Asphalt, the lowest responsible bidder.  No appeal/protest letters were received.

 

This Project will have a 10 percent contingency fund of $82,981 to compensate the contractor for verified quantity overruns, as well as changes in the contract under certain circumstances.  Under an established formula based on the contract amount, Public Contract Code section 20142 allows the Board to authorize the Director of the Department to order changes in the contract, including for unforeseen conditions or design shortfalls, should they become necessary in the future, for a total amount not to exceed $53,990 of the $82,981 contingency fund.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Aaron Gest, Deputy County Counsel, 387-5455) on June 27, 2023; Purchasing (Jason Cloninger, Lead Buyer, 387-8258) on June 27, 2023; Finance (Carl Lofton, Administrative Analyst, 387-5404) on July 7, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on July 7, 2023.