REPORT/RECOMMENDATION TO THE BOARD OF DIRECTORS
OF SAN BERNARDINO COUNTY FIRE PROTECTION DISTRICT
AND RECORD OF ACTION
July 23, 2024
FROM
DAN MUNSEY, Fire Chief/Fire Warden, San Bernardino County Fire Protection District
DON DAY, Director, Project and Facilities Management Department
SUBJECT
Title
Amendment and Change Order to Contract with Oakview Constructors, Inc. for the County Fire Station 226 New Build Project in San Bernardino
End
RECOMMENDATION(S)
Recommendation
Acting as the governing body of the San Bernardino County Fire Protection District:
1. Approve Amendment No. 1 to Contract No. 23-835 with Oakview Constructors, Inc., in the amount of $134,787, increasing the contract from $7,682,000 to $7,816,787, for the County Fire Station 226 New Build Project in San Bernardino (Four votes required).
2. Find that the specifications in Change Order No. 1 to Contract No. 23-835 with Oakview Constructors, Inc. calling for the installation of the Westnet station alerting system, and not allowing substitution of an equal product, is acceptable under Public Contract Code section 3400(c)(2), as installation of this system is required in order to match other products in use on a particular public improvement either completed or in the course of completion.
3. Approve Change Order No. 1 to Contract No. 23-835 with Oakview Constructors, Inc., in the amount $178,223, increasing the contract from $7,816,787 to a total of $7,995,010, for the County Fire Station 226 New Build Project in San Bernardino (Four votes required).
4. Authorize the Fire Chief/Fire Warden or Deputy Fire Chief to accept the work performed by Oakview Constructors, Inc. for the Westnet station alerting system when complete and sign the Acceptance Test Plan and Final System Acceptance Certificate.
(Presenter: Don Day, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally Responsible and Business-L...
Click here for full text