Subject: Amendment to Cooperative Agreement with the City of Hesperia for the Ranchero Road Corridor Widening Project, Hesperia area
Attachments: 1. MAP-PW-Trans 3-24-20 Amend Coop Agr with City of Hesperia for Ranchero Road Corridor, 2. CON-PW-Trans 3-24-20 Amend Coop Agr with City of Hesperia for Ranchero Road Corridor, 3. Item #39 Executed BAI, 4. 11-424 A1 Executed Agreement

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF THE COUNTY OF SAN BERNARDINO

AND RECORD OF ACTION

 

March 24, 2020

 

FROM

BRENDON BIGGS, Interim Director, Department of Public Works - Transportation

         

SUBJECT                      

Title

Amendment to Cooperative Agreement with the City of Hesperia for the Ranchero Road Corridor Widening Project, Hesperia area

End

 

RECOMMENDATION(S)

Recommendation

Approve Amendment No. 1 to Cooperative Agreement No. 11-424, effective upon execution by both Parties, with the City of Hesperia, revising the agreement amount by $16,950,001 (from $1,154,156 to $18,104,157) and adding the construction phase to the agreement for the Ranchero Road Corridor Widening Project, in the Hesperia area.

(Presenter: Brendon Biggs, Interim Director, 387-7906)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Pursue County Goals and Objectives by Working with Other Agencies.

 

FINANCIAL IMPACT

Approval of Amendment No. 1 will not result in the use of additional Discretionary General Funding (Net County Cost). In 2018-19 the County of San Bernardino (County) Board of Supervisors (Board) allocated Net County Cost in the amount of $5,320,000 for the Project. The total cost for the Ranchero Road Corridor Widening Project east of Mariposa Road to 7th Avenue, in the Hesperia area (Project), including the project approval and environmental documents (PA/ED), design and construction was revised and estimated to be $35,955,300. This amount excludes costs for right-of-way and the construction costs for a bridge located within the City’s jurisdictional boundary. The County and City are each responsible for right-of-way activities within their respective boundaries and related costs. The City is solely responsible for the bridge activities and the associated costs.

 

This Amendment increases the City of Hesperia (City) share of the Project cost by $7,554,482 (from $577,078 to $8,131,560), and increases the County’s share of the Project cost by $9,395,519 (from $577,078 to $9,972,597). The County’s share of the Project cost will be funded by Net County Cost ($5,320,000), Measure “I” 2010-2040 Local Pass-Through funds ($2,640,527), Regional Development Impact Fees collected from the Victor Valley subarea ($860,000), Senate Bill 1 Local Partnership Program (LLP) grant funds ($980,000) and California Department of Resources Recycling and Recovery (CalRecycle) grant funds ($172,070). Sufficient appropriation and revenue are included in the Department of Public Works (Department) 2019-20 Road Operations budget and will be included in future recommended budgets.

 

The County and City’s total share of the Project cost is $18,104,157, and the remaining cost of $17,851,143 will be funded with the San Bernardino County Transportation Authority (SBCTA) Public Share, as stipulated by the SBCTA Measure “I” 2010-2040 Expenditure Plan and Nexus Study. Pursuant to Measure “I” policy, the City, as lead agency, and SBCTA will enter into a separate funding agreement for the SBCTA share of the Project cost.

 

Furthermore, it is anticipated that the LPP grant and California Department of Resources Recycling and Recovery (CalRecycle) Grant funds awarded to the City will be received and will be applied to both the County and City shares of the Project cost, reducing their final contribution. Receipt of the LPP and CalRecycle grant funds is contingent upon the Project meeting specified Project milestones. The LPP grant amount is estimated to be $3,900,000 and the CalRecycle grant amount is estimated to be $288,000. The LPP grant is a competitive grant program that provides funding for certain projects in locations that have development mitigation fee programs. The CalRecycle grant provides Rubberized Pavement Grant Program funds to local agencies to use rubberized asphalt concrete, in an effort to reduce, recycle, and reuse waste tires generated in California.

 

BACKGROUND INFORMATION

Amendment No. 1 to the Agreement  adds the construction phase to the Agreement; and revises the County and City’s share of the Project cost estimate by $16,950,000 (from $1,154,156 to $18,104,157). The County’s share is estimated to be $9,972,597 and the City’s share is estimated to be $8,131,560.

 

Significant changes have occurred during the environmental and design phases.  These include replacement of existing pipe culverts with concrete box culverts and additional design work due to construction work near Escondido Avenue and Oak Hills High School, and the need for additional pavement surface improvements to the existing roadway. In addition, after existing underground utilities were examined, a waterline was deemed in conflict with the Project and will require replacement. These changes necessitated additional design work, which also increased the Project’s design and construction costs.

 

The Project consists of widening Ranchero Road from two through lanes to an interim five-lane road that has four through lanes and one continuous left turn lane. The asphalt concrete on the pavement will be replaced, and the culverts at several locations will be replaced and constructed anew. Traffic signals will be installed at the intersections of Ranchero Road with Maple Avenue, Cottonwood Avenue, and 7th Avenue within the City limits, and other appurtenant work will be done at the Project location. Construction is anticipated to commence in the winter of 2020.

 

This item meets the County and the Chief Executive Officer goals and objectives by working with the City of Hesperia in constructing roadway improvements to mitigate traffic congestion surrounding the Project area.

 

On June 28, 2011 (Item No. 95) the Board approved County Contract No. 11-424 with the City for the Project Approval and Environmental Documentation and design phases of the Project. The estimated cost for these two components was $1,154,156, wherein the County and City split the cost evenly at $577,078 each. City serves as lead agency for the Project.

 

The County and City are each responsible for right-of-way activities within their respective boundaries and the related costs, and therefore, right-of-way costs are not part of this Amendment No. 1. On July 11, 2017 (Item No. 21), the Board approved a Project Funding Agreement with the SBCTA wherein County shall receive up to $1,456,650 in Major Local Highways Program funds from SBCTA for SBCTA’s share (58.5%) of right-of-way costs associated with properties within the County unincorporated area of Hesperia. The County’s share (41.5%) under the agreement would have been $1,033,350 in developer fees or an internal loan from Department funds to be paid back as developer fees are collected. The total estimated cost at the time of the right-of-way funding agreement execution was $2,490,000.

 

The current cost for right-of-way activities within the County’s jurisdiction has been revised downward and is now estimated to be $1,151,971. The reduction in right-of-way cost is the result of certain properties no longer being required for the Project. The revised cost estimate includes up to $972,771 to be paid to the Union Pacific Railroad Company for improvement work at the railroad crossing on Ranchero Road, land cost of $79,200, plus $100,000 budgeted for escrow and title fees, and the Department of Real Estate Service staff time.

 

Except as amended by this Amendment No. 1, all other terms and conditions of Cooperative Agreement No. 11-424 shall remain the same. The City of Hesperia approved Amendment No. 1 to County Contract 11-424 at its regular council meeting on March 17, 2020.

 

PROCUREMENT

Not applicable.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Suzanne Bryant, Deputy County Counsel, 387-5455) on February 28, 2020; Finance (Jessica Trillo, Administrative Analyst, 387-4222) on March 6, 2020; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on March 8, 2020.