REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
August 05, 2025
FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation
SUBJECT
Title
Contract with TVR Construction Engineering, Inc. for the Olive Street Project in the Colton Area
End
RECOMMENDATION(S)
Recommendation
1. Award construction Contract to TVR Construction Engineering, Inc. in the amount of $404,178.10 for the Olive Street Project in the Colton area.
2. Authorize a contingency fund of $40,417 for the Olive Street Project in the Colton area.
3. Authorize the Director of the Department of Public Works to approve the expenditure of the contingency fund of $40,417 for verified quantity overruns for this unit-priced construction contract.
4. Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the contract, for a total amount not to exceed $32,708 of the $40,417 contingency fund, pursuant to Public Contract Code Section 20142.
5. Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Noel Castillo, Director, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Olive Street Project in the Colton Area (Project) will be funded with Community Development Block Grant funds administered by the Community Development and Housing Department and with City of Colton (City) local funds. Sufficient appropriation and revenue are included in the Department of Public Works (Department) 2025-26 Road Operations budget (6650002000 H15201).
BACKGROUND INFORMATION
The Project involves sid...
Click here for full text