Subject: Appraisal and Acquisition of Easements across Private Property for the Ranchero Road Corridor Widening Project in the Unincorporated Oak Hills Area
Attachments: 1. MAP RESD-DPWT-032420-App & Acq of Drainage Easements for Ranchero Road, 2. Item #47 Executed BAI

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF THE COUNTY OF SAN BERNARDINO

AND RECORD OF ACTION

 

March 24, 2020

 

FROM

TERRY W. THOMPSON, Director, Real Estate Services Department

BRENDON BIGGS, Interim Director, Department of Public Works - Transportation

 

SUBJECT

Title                     

Appraisal and Acquisition of  Easements across Private Property for the Ranchero Road Corridor Widening Project in the Unincorporated Oak Hills Area

End

 

RECOMMENDATION(S)

Recommendation

1.                     Approve Appraisal No. 20-02 dated February 27, 2020, a copy of which is on file with the Real Estate Services Department.

2.                     Authorize the acquisition of two permanent drainage and flowage easements, and one permanent road easement, over portions of four parcels, [Assessor Parcel Numbers (APN) 3039-511-03, 3039-511-04, 0357-272-03, and 0357-272-04] from three property ownerships for the Ranchero Road Corridor Widening Project in the Unincorporated Oak Hills area.

3.                     Authorize the Director of the Real Estate Services Department to execute the acquisition agreements for the easement interests with three property ownerships for a total purchase amount of $8,100, and any other documents necessary to complete these transactions.

 (Presenter: Terry W. Thompson, Director, 387-5252)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Operate in a Fiscally-Responsible and Business-Like Manner.

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Provide for the Safety, Health and Social Service Needs of County Residents.

Pursue County Goals and Objectives by Working with Other Agencies.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost).  The County of San Bernardino’s (County) total cost to acquire two permanent drainage and flowage easements, and one permanent road easement is $8,100, plus escrow and title fees. This represents the second phase of acquisitions for the Ranchero Road Corridor Widening Project (Project) in the unincorporated Oak Hills area. The County and City of Hesperia (City) are joint participants on the Project. Each agency will be responsible for right of way acquisition and utility relocation within their own jurisdiction. The budgeted County’s portion for right of way cost of the Project is $2,490,000, of which San Bernardino County Transportation Authority (SBCTA) will reimburse $1,456,650 to the County. The remaining $1,033,350 will be funded through the County’s Local Measure I Victor Valley Subarea funds. Sufficient appropriation is included in the 2019-20 Road Operations budget (6650002000 H14943). SBCTA reimbursement will be funded by Measure ”I” Major Local Highway Program (MLHP) - Victor Valley Subarea funds.

 

BACKGROUND INFORMATION

This item will approve the appraisal and acquisition of two permanent drainage and flowage easements, and one permanent road easement from three property owners for construction of the Project and represents the second phase of acquisitions. Additional acquisitions will be brought forward in future phases.

 

The County Department of Public Works-Transportation (DPW-T) is working jointly with the City  on the Ranchero Road Widening Project to widen Ranchero Road from two through lanes to an interim five-lane road that has four through lanes and one continuous left turn lane, between east of Mariposa Road to 7th Avenue. The City is the Lead Agency of the Project, and after right of way acquisitions, the City shall resume as Lead Agency of the construction component of the Project.

 

On June 28, 2011 (Item No. 95), the Board approved County Contract No. 11-424 with the City for Project Approval and Environmental Documentation and design. The estimated cost for these two components was $1,154,156, wherein the County and the City split the cost evenly at $577,078 each. The City serves as lead agency for the Project.

 

On July 11, 2017, the Board approved Project Funding Agreement No. 17-624 (Item 21) between the County and SBCTA for the County to receive reimbursement in the amount of $1,456,650 from Measure ”I” MLHP - Victor Valley Subarea funds for the right of way and utility relocation work. SBCTA Board of Directors approved this Funding Agreement on June 7, 2017.

 

On February 11, 2020 (Item 57), the Board adopted Resolution 2020-10 pursuant to the California Environmental Quality Act (CEQA).

 

On March 10, 2020 (Item 52), the Board approved appraisal and acquisition of the first phase of acquisitions that included four permanent roadway easements and three temporary construction easements from four property owners and an Authorization and Reimbursement Agreement Public Road Crossing Improvements - Surface, Signal and Signal Interconnect with Union Pacific Railroad Company (UPRR) to improve the UPRR’s existing, at-grade crossing area as part of the Project.

 

DPW-T requires additional permanent and temporary easements for drainage and flowage, and roadway purposes, and a temporary construction easement totaling 45,145 square feet across four parcels from three individual property owners to complete the County portion of this second acquisition phase of the Project. DPW-T requested the Real Estate Services Department (RESD) assist with the appraisal and acquisition of the needed property rights.

 

The portions of land to be acquired from the four parcels and three ownerships are described as follows:

 

 Property Owner

Exhibit No. and Type of Easement

 APN

Total Area to be Acquired (sq. ft.)

Bakolas

E-8

3039-511-03, 04

26,094

Castillo

DE-26B

0357-272-03

6,817

Chennapoola Ltd Partnership

DE-27B

0357-272-04

12,234

 

An appraisal (No. 20-02) dated February 27, 2020 was completed by, and maintained on file with, RESD.  The appraisal establishes the amount of just compensation to be paid to the three property owners for the easement interests necessary to construct the Project and totals $8,100 for the three ownerships. 

 

The City applied for State funding, SB 1 LPP Grant, which is administered by California Transportation Commission, in the amount of $3.9 million and received notice of award in May 2018.  The County stands to receive approximately $1 million from this grant to assist with construction of the Project.  The grant was approved by the California Transportation Commission (CTC) for one year, until May 2019, and is contingent on the acquisition of all right of way necessary for construction of the Project.  The City requested and received a one-year extension from the CTC, to May 2020, in order to provide additional time to design the Project and acquire the right of way.  The Project cannot proceed to the construction phase until all requirements for the right-of-way have been completed.

 

The County is responsible for acquiring the right of way from properties located within the unincorporated area and the City is responsible for acquiring the right of way from properties within the City portion of the project.  The SB 1 LPP guidelines specify that any extensions granted cannot be extended a second time.  Therefore, in order to meet the funding deadline, the County must deliver all documents demonstrating possession of the property for the Project to the City by April 1, 2020 in order to meet the deadline for local agencies to submit Right-of-Way certification to Caltrans, per CTC guidelines, to receive an allocation of LPP funds for construction.

 

Approval of this item will authorize RESD to make offers and acquire the necessary right of way in conformance with all applicable provisions of the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, as amended, Government Code section 7260 et seq., corresponding regulations, and County Policy No. 12-20.

 

On February 11, 2020 (Item No. 57), the Board adopted a Resolution No. 2020-10 considering the Final Environmental Impact Report, the Mitigation Monitoring Reporting Program, and Findings of Fact and Statement of Overriding Considerations for the Project in compliance with CEQA Guidelines 15093.

 

PROCUREMENT

Not applicable.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Robert Messinger, Principal Assistant County Counsel, and Suzanne Bryant, Deputy County Counsel, 387-5455) on February 26, 2020;     DPW-T (Mervat Mikhail, Chief Transportation Design, 387-7940) on February 11, 2020; Purchasing (Michelle Churchill, Buyer III, 387-2070) on February 19, 2020; Finance (Jessica Trillo, Administrative Analyst, 387-4222 and Wen Mai, Principal Administrative Analyst, 387-4020) on March 16, 2020; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on March 17, 2020.

 

(NS: 677-8388)