Skip to main content
File #: 4665   
Type: Consent Status: Passed
File created: 8/3/2021 Department: Public Works-Transportation
On agenda: 8/10/2021 Final action: 8/10/2021
Subject: Amendment to the Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan Project List
Attachments: 1. ATT-PW-Trans 8-10-21 Amend Measure I Local Street Pass-Thru 5-Year CIP Project List, 2. ATT-PW-Trans 8-10-21 Amend Measure I Local Street Pass-Thru 5-Year CIP Project List - Road List, 3. RES-PW-Trans 8-10-21 Amend Measure I Local Street Pass-Thru 5-Year CIP Project List, 4. Item #29 Executed BAI, 5. 2021-150 Executed Resolution
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

August 10, 2021

FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation

SUBJECT
Title
Amendment to the Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan Project List
End

RECOMMENDATION(S)
Recommendation
Adopt Resolution approving Amendment No.1 to the San Bernardino County Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan project list (Attachment A) for 2020-21 through 2024-25 to add projects to the list and modify the scope of certain projects.
(Presenter: Brendon Biggs, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan (CIP) project list (Attachment A) identifies projects designated to utilize current and future Measure "I" sales tax revenues. The total estimated cost of projects listed in the amended five-year CIP project list will increase from $48,507,260 to $49,907,260. Sufficient appropriation and revenue for the added and revised projects are included in the Department's 2021-22 Transportation Budget and will be included in future recommended budgets.

BACKGROUND INFORMATION
Pursuant to the Measure "I" program, described below, the Amendment to the San Bernardino County Measure "I" Local Street-Pass-Through Funds Five-Year CIP project list (Attachment A) for 2020-21 through 2024-25 will be submitted to the San Bernardino County Transportation Authority (SBCTA) in order to utilize current and future Measure "I" sales tax revenue for the projects listed in Attachment A.

On November 7, 1989, (Measure "I" 1990-2020 Ordinance No 89-1) was passed by voters of San Bernar...