REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION
January 28, 2020
FROM
BRENDON BIGGS, Interim Director, Department of Public Works -Transportation
SUBJECT
Title
Contract with WEKA, Inc. for the 39th Street Storm Drain Replacement Project, San Bernardino Area
End
RECOMMENDATION(S)
Recommendation
1. Award a construction contract to WEKA, Inc. (Highland, CA), in the amount of $418,998 for the 39th Street Storm Drain project (Project) in the San Bernardino area.
2. Authorize a contingency fund of $41,899 for the Project.
3. Authorize the Director of Public Works to approve the expenditure of the contingency fund of $41,899 for verified quantity overruns for this unit priced construction contract.
4. Authorize the Director of Public Works to order any necessary changes or additions in the work being performed under the contract for a total amount not to exceed $33,449 of the $41,899 contingency fund, pursuant to Public Contract Code section 20142.
5. Authorize the Director of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Brendon Biggs, Interim Director, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Department of Public Works (Department) is funded by Gas Tax revenues, fees, and other state and local funding. The construction contract of $418,998 and contingency fund of $41,899 will be funded with Gas Tax revenue. Sufficient appropriation is included in the 2019-20 Road Operations budget (6650002000 18H14960).
BACKGROUND INFORMATION
The Project consists of removing existing corrugated metal pipe storm drains and drainage structures, and replacing with a new reinforced concrete box culvert and drainage structures. The Project is located on 39th Street at the intersection of Conejo Drive (south), in the San Bernardino area. The Project also includes upgrading pedestrian curb ramps to comply with the current Americans with Disabilities Act (ADA) guidelines and the replacement of sidewalk, curb, gutter and paving.
The Project aligns with the County and Chief Executive Officer’s goals and objectives to ensure the development of a well-planned, balanced, and sustainable County and provide for the safety of County residents by improving street drainage and access for all pedestrians and removing architectural barriers for those with mobility disabilities. All work for the Project will be done within the existing road right-of-way.
Environmental staff of the Department has reviewed this Project and determined that a categorical exemption in accordance with the California Environmental Quality Act (CEQA) Guidelines, Title 14 of the California Code of Regulations, Section 15302 is appropriate. This exemption allows for the replacement or reconstruction of existing structures or facilities that have substantially the same purpose and capacity as the structure replaced. The Notice of Exemption was filed on October 23, 2019.
Following Board of Supervisors (Board) approval of this item, construction is anticipated to commence mid-March of 2020 and be completed by mid-May of 2020.
PROCUREMENT
On October 22, 2019 (Item No. 27), the Board approved the Project’s plans and specifications, as well as authorized the Director of the Public Works to advertise the Project for bids. This Project was advertised in the Daily Press on November 12, 2019, in the Precinct Reporter on November 14, 2019, and released on the County Electronic Procurement Network (ePro) on November 12, 2019. Notice inviting bids was also provided to specified construction trade journals as required by Public Contract Code section 22036. On December 11, 2019, the following four bids were received:
|
Contractor |
Location |
Total Bid |
|
WEKA, Inc. |
Highland, CA |
$418,998 |
|
H&H General Contractors, Inc. |
Highland, CA |
$433,979 |
|
All American Asphalt |
Corona, CA |
$525,450 |
|
Genuine Engineering, Inc. |
Corona, CA |
$591,379 |
The Department has reviewed the bids received and determined that they are responsive and recommends entering into a contract with WEKA, Inc., the lowest responsible bidder. No appeal/protest letters were received.
This Project will have a 10 percent contingency fund of $41,899 to compensate the contractor for verified quantity overruns, as well as changes in the contract under certain circumstances. Under an established formula based on the contract amount, Public Contract Code section 20142 allows the Board to authorize the Director of Public Works to order changes in the contract, including for unforeseen conditions or design shortfalls, should they become necessary in the future, for a total amount not to exceed $33,449 of the $41,899 contingency fund.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Suzanne Bryant, Deputy County Counsel, 387-5455) on January 2, 2020; Purchasing (Jason Cloninger, Lead Buyer, 387-8258) on January 2, 2020; Finance (Jessica Trillo, Administrative Analyst, 387-4222) on January 7, 2020; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on January 7, 2020.