REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION
March 24, 2020
FROM
TERRY W. THOMPSON, Director, Real Estate Services Department - Project Management
SUBJECT
Title v
Award Construction Contract to Roadway Engineering & Contracting, Inc. for the Whitney Young - Modular Project
End
RECOMMENDATION(S)
Recommendation
1. Approve the following addenda to the Bid Documents for the Whitney Young - Modular Project.
a. Addendum No. 1 to the bid documents, issued December 20, 2019, which added Resolution No. 2019-067-PC to the bid documents.
b. Addendum No. 2 to the bid documents, issued January 10, 2020, which revised the bid closing date from February 5, 2020 at 2:00 p.m. to February 13, 2020 at 2:00 p.m., revised the bid documents, added project drawings and specifications, added fire department requirements, added WQMP Plan and added the Hydrology Study.
c. Addendum No. 3 to the bid documents, issued February 7, 2020, which revised the civil drawings, added a submittal for basis of design and provided project narrative, and responses to contractors’ requests for information.
2. Award a construction contract in the amount of $1,243,400 to Roadway Engineering & Contracting, Inc., Inc. of Fontana, CA 92337 for the Whitney Young - Modular Project (No. 10.10.0572), located at 1755 W Maple Street, San Bernardino, CA 92411.
3. Authorize the Director of the Real Estate Services Department to order any necessary changes or additions in the work being performed under the contract for a total not to exceed $74,670, pursuant to Public Contract Code Section 20142.
4. Authorize the Director of the Real Estate Services Department to accept work when 100% complete, execute, and file the Notice of Completion.
(Presenter: Terry W. Thompson, Director, 387-5252)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like Manner.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Whitney Young - Modular Project (Project) budget is comprised of the following components:
|
Design |
$ 109,260 |
|
Materials Testing/ Inspection |
$ 32,231 |
|
Project Management |
$ 107,000 |
|
Construction |
$ 1,365,008 |
|
Construction Contingency |
$ 136,501 |
|
Total Project Budget |
$ 1,750,000 |
The total Project budget of $1,750,000 is funded from the Preschool Services Enterprise Capital Fund and is included as part of the 2019-20 Capital Improvement Program (CIP) budget.
BACKGROUND INFORMATION
The recommended action will award a construction contract to Roadway Engineering & Contracting, Inc., (Roadway) for the Project, which will provide two 24’ x 60’ new mobile modular classroom buildings, accessible concrete walkway, new playground area, new steel picket fence, chain link fence and gates for the perimeter of the new classrooms and playground for County Preschool services on existing County Housing Authority property located at 1755 W Maple Street, San Bernardino, CA 92411.
On December 17, 2019 (Item No. 55), the Board found that the Project is exempt under California Environmental Quality Act (CEQA) Guidelines, Section 15303, subsections (c) and (e), Class 3 - New Construction or Conversion of Small Structures, and directed the Clerk of the Board to file and post the Notice of Exemption for the Project.
This Project is consistent with County Administrative Office approved CIP Request No. 17-279.
PROCUREMENT
On December 17, 2019 (Item No. 55), the Board authorized the Real Estate Services Department - Project Management (PM) to advertise for competitive bids for the Project. On December 20, 2019, PM advertised in the Daily Press, six plan rooms, PM's website and on the County of San Bernardino's Electronic Procurement Network (ePro). On January 7, 2020, 32 contractors attended a mandatory pre-bid meeting. On December 20, 2019, Addendum No. 1 was issued which added Resolution No. 2019-067-PC to the bid documents. On January 10, 2020, Addendum No. 2 was issued which revised the bid closing date from February 5, 2020 at 2:00 p.m. to February 13, 2020 at 2:00 p.m., revised the bid documents, added project drawings and specifications, added fire department requirements, added WQMP and added the hydrology report. On February 7, 2020, Addendum No. 3 was issued, which revised the civil drawings, added a submittal for basis of design and provided a project narrative, and responded to contractors’ request for additional information.
On February 13, 2020, the following eight bids were received.
|
Contractor |
Location |
Bid |
|
Roadway Engineering & Contracting, Inc. |
Fontana, CA |
$ 1,243,400 |
|
Hamel Contracting , Inc. |
Murrieta, CA |
$ 1,365,008 |
|
Caliba Inc. |
Huntington Beach, CA |
$ 1,478,000 |
|
Gilman Builders, Inc. |
Irvine, CA |
$ 1,684,000 |
|
Edra Construction, Inc. |
Glendora, CA |
$ 1,761,000 |
|
Cornerstone Renovation, Inc. |
Rancho Cucamonga, CA |
$ 1,824,000 |
|
Jergensen Construction |
Oak Hills, CA |
$ 1,862,000 |
|
Dalke & Sons Construction, Inc. |
Riverside, CA |
$ 1,988,680 |
On February 14, 2020, PM received a formal bid protest from Hamel Contracting Inc. (Hamel). The basis of the protest was that the bid submitted by Roadway did not satisfy the licensing requirements contained in Business and Professions Code Section 7057. PM has evaluated the bid protest with the following result. Section 7057(c) provides that “A general building contractor shall not contract for any project that includes a fire protection system . . . unless the general building contractor holds the appropriate license or subcontracts with the appropriately licensed contractor.” This Project includes a deferred submittal for a new fire alarm and fire suppression system connected to the existing fire alarm control panel. Per applicable regulations, a Fire Protection Contractor must have a C-16 license. Roadway does not hold a C-16 license, but did subcontract with Global Modular, Inc., who in turn sub-subcontracted with J.R. Wagner Fire Protection, Inc. (J.R. Wagner) for the fire protection work. J.R. Wagner holds a C-16 license. Project Management therefore found Hamel’s bid to be unsubstantiated.
PM recommends the Board award the construction contract to Roadway Engineering & Contracting, Inc., the lowest responsive and responsible bidder. This Project is consistent with County Administrative Office approved CIP Request No. 17-279.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Katherine Hardy, Deputy County Counsel, 387-5437) on February 27, 2020; Preschool Services (Phalos Haire, Interim Director, 383-2005) on February 27, 2020; Purchasing Department (Cody Leslie, Buyer II, 387-2065) on February 27, 2019; Project Management (Jennifer Costa, Assistant Director, 387-5000) on February 27, 2020; Finance (Wen Mai, Principal Administrative Analyst, 387-4020) on March 3, 2020; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on March 9, 2020.
(MM: 531-1582)