Subject: Amendment to Contract with Kimley-Horn and Associates for County Service Area 82 - Searles Valley Sewer Improvement Project
Attachments: 1. R1-CON-MULTI-BGCSA-102423 CSA 82 Searles Valley Sewer Improvement Project Contract Extension, 2. Item #86 Executed BAI, 3. 23-259 A-1 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF THE FOLLOWING:

SAN BERNARDINO COUNTY

 BOARD GOVERNED COUNTY SERVICE AREAS

AND RECORD OF ACTION

 

October 24, 2023

 

FROM

BRENDON BIGGS, Director, Department of Public Works - Special Districts 

         

SUBJECT                      

Title                     

Amendment to Contract with Kimley-Horn and Associates for County Service Area 82 - Searles Valley Sewer Improvement Project

End

 

RECOMMENDATION(S)

Recommendation

1.                     Acting as the governing body of County Service Area 82 - Searles Valley:

a.                     Approve Amendment No.1 to Contract No. 23-259 with Kimley-Horn and Associates for professional engineering design services associated with the County Service Area 82 Searles Valley Sewer Improvement Project, adding additional language in connection with Senate Bill 1439 regarding consultant reporting information, and extending the term by three years for a revised contract period of March 28, 2023 through December 31, 2026, with no changes to the contract amount of $524,157.

b.                     Authorize the Auditor-Controller/Treasurer/Tax Collector to post budget adjustments of $6,020,078, as detailed in the Financial Impact Section, for the County Service Area 82 Searles Valley Sewer Improvement Project (Four votes required).

2.                     Acting as the governing body of San Bernardino County, authorize the Auditor-Controller/Treasurer/Tax Collector to post budget adjustments of $6,020,078, as detailed in the Financial Impact Section, needed to provide funding for the County Service Area 82 Searles Valley Sewer Improvement Project (Four votes required).

(Presenter: Brendon Biggs, Director, 387-7906)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost).  This amendment is for an extension to the contract term with no increase in the contract amount of $524,157.

 

The County Service Area 82 Searles Valley (CSA 82) Sewer Improvement Project (Project), including the costs of Contract No. 23-259 with Kimley-Horn and Associates, is funded through a $6,034,682 allocation from the County’s American Rescue Plan Act (ARPA) Coronavirus Local Fiscal Recovery Fund (CLFRF) for eligible costs. The Project and its funding allocation were approved by the Board of Supervisors (Board) on March 28, 2023 (Item No. 65). Because the 2023-24 recommended budget submittal was prior to this date, appropriation for the Project was not included in the 2023-24 budget. Therefore, the following budget adjustments are needed:

 

 

Fund Center

Commitment Item

Description

Action

Amount

 ARPA Capital Improvement Program (CIP) for Special Districts:

1050003509

54104010

Improvements to Land

Increase

$6,020,078

1050003509

40909975

Operating Transfers In

Increase

$6,020,078

 San Bernardino County - ARPA CLFRF:

1100001078

52002135

Special Dept Expense

Decrease

$6,020,078

1100911078

55305030

Operating Transfers Out

Increase

$6,020,078

 Note: During 2022-23, the Project incurred costs of $14,604.

 

Appropriation for the Project will be included in future recommended budgets of the Department of Public Works - Special Districts (Department) ARPA Capital Improvement Projects (CIP) Fund, as needed.

 

BACKGROUND INFORMATION

CSA 82 was established by the San Bernardino County Board of Supervisors on June 28, 1976 to provide, among other things, sewer services for the communities of Trona and Pioneer Point, east of Ridgecrest and adjacent to the western boundary of Death Valley National Park. The Department’s Water and Sanitation Division (Division) directly manages, operates, and maintains sewer services for CSA 82.

 

The Division currently maintains a 12-inch primary sewer effluent line, including two septic tank treatment facilities and 52 manholes for CSA 82. The effluent line spans from Pioneer Point (north) to Trona (south) as part of the overall sewerage system. The 12-inch effluent line covers approximately 13,900 feet, along the eastern side of Trona Road, encompassing 18 manhole locations. The effluent line was constructed in 1979 and needs reconstructing and/or replacing worn, damaged, and deleterious segments of effluent sewer line and manhole structures. The Division has preliminarily identified and prioritized 11,317 feet of the effluent line and up to 12 manholes that need replacement. The Project will add up to six manholes to reduce spacing to a consistent 500 to 600 feet allowing for additional access points for maintenance and inspection purposes pursuant to industry standards.

 

On March 28, 2023 (Item No. 65), following a successful competitive procurement, the Board approved Contract 23-259 (Contract) with Kimley-Horn and Associates (Kimley-Horn) to provide professional engineering design services for the Project in the amount of $524,157, for a contract term from March 28, 2023, through November 23, 2023.

 

This item seeks approval of Amendment No. 1 (Amendment) to extend the Contract from November 23, 2023 through December 31, 2026.  The Amendment will provide Kimley-Horn, at no added cost, with additional and sufficient time to complete environmental permitting, final design, and construction support for the Project, which must be completed by December 31, 2026.  The Amendment also adds language in connection with Senate Bill 1439 concerning consultant reporting information.

 

This item also seeks approval for budget adjustments that are needed to proceed with the Project. On March 28, 2023 (Item No. 65), the board approved the CIP project for $6,034,682. During 2022-23, the project incurred $14,604 in expenditures for staff time related to this project. As a result, a budget adjustment of $6,020,078 is being requested for 2023-24 to carry forward the budget for this Project.

 

PROCUREMENT

Not applicable.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Aaron Gest, Deputy County Counsel, 387-5455) on September 27, 2023; Auditor-Controller/Treasurer/Tax Collector (Charlene Huang, General Accounting Manager, 382-7022) on September 20, 2023; Finance (Tom Forster, Administrative Analyst, 387-4635 and Guy Martinez, ARPA Compliance Officer, 387-5428) on October 3, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on October 5, 2023.