REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
February 28, 2023
FROM
DON DAY, Director, Project and Facilities Management Department
JACQUELYN GREENE, Director, Preschool Services Department
SUBJECT
Title
Amendment to Construction Contract with Cornejo Construction Company for Countywide Preschool Services Department Improvement Project Phase II - Ontario Maple Perimeter Fence Project
End
RECOMMENDATIONS
Recommendation
Approve Amendment No.1 to Contract No. 22-032 with Cornejo Construction Company, in the amount of $217,915, increasing the construction contract from $334,896 to a total of $552,811, for the Countywide Preschool Services Department Improvement Project Phase II - Ontario Maple Perimeter Fence Project located at 555 Maple Street in Ontario (Four votes required).
(Presenter: Don Day, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Provide for the Safety, Health, and Social Service Needs of County Residents.
FINANCIAL IMPACT
This item does not require Discretionary General Funding (Net County Cost). The Countywide Preschool Services Department (PSD) Improvement Project Phase II - Ontario Maple Perimeter Fence Project (Project) (WBSE 10.10.0315) budget of $2,043,778 is funded with PSD Federal Head Start Funds, previously approved by the Board of Supervisors (Board) as part of the 2022-23 Capital Improvement Program (CIP) and is comprised of the following components:
|
Description |
Amount |
|
Construction Phase I - New Modular Building |
1,291,277 |
|
Construction Phase II - New Perimeter Fencing |
752,501 |
|
Total Project Budget |
$2,043,778 |
Phase II of the Project budget is comprised of the following components:
|
Description |
Amount |
|
Project Design |
60,040 |
|
Project Management, Inspection, and Testing |
108,745 |
|
Construction |
552,811 |
|
Contingency |
30,905 |
|
Total Phase II Project Budget |
$752,501 |
BACKGROUND INFORMATION
The Project, located in the City of Ontario, includes the procurement and installation of new perimeter fence to address child privacy concerns and comply with California Code of Regulations Title 22 Division 12 Chapter 1 Article 7 Section 101238.2 Outdoor Activity Space, Subsection (g).
Amendment No. 1 will increase the contract amount with Cornejo Construction Company (Cornejo) by $217,915, to cover the escalation in equipment costs for the new fence and all its components due to a change in economic conditions caused by inflation and supply chain issues related to the COVID-19 pandemic. Also, the increase in the contract amount covers the additional labor, materials, and equipment required to install prefabricated metal panels, as requested by PSD.
On January 25, 2022 (Item No. 43), the Board awarded Cornejo the Project construction contract, in the amount of $309,046 to provide privacy fencing from January 25, 2022 to May 3, 2023, and approved the Director of Real Estate Services Department (RESD) to order any necessary changes or additions in the work being performed under the contract, for a total amount not to exceed $27,952, pursuant to Public contract Code Section 20142. Of the amount authorized for change orders, $25,850 was expended on January 6, 2023.
This Project is consistent with County Administrative Office approved CIP request No. 17-266.
PROCUREMENT
On September 21, 2021 (Item No. 40), the Board authorized RESD-Project Management (PM), now known as Project and Facilities Management Department (PFMD), to advertise for competitive bids for the Project. On September 24, 2021, RESD-PM advertised in the Daily Press, six plan rooms, RESD-PM’s website, and on San Bernardino County’s Electronic Procurement Network (ePro). On November 03, 2021, four bids were received and on January 25, 2022, (Item No. 43), the Board awarded a construction contract to Cornejo, the lowest responsive and responsible bidder.
The unanticipated additional cost items requiring Amendment No. 1 are related to events that took place after the competitive bid processes that resulted in the original contract with Cornejo. Although no additional procurement activities are required, Board approval is required for this amendment to the contract with Cornejo, per Public Contract Code sections 20136.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Katherine Hardy, Deputy County Counsel, 387-5455) on January 26, 2023; Preschool Services (Jacquelyn Greene, Director, 383-2025) on January 26 , 2023; Purchasing (Bruce Cole, Supervising Buyer, 387-2148) on January 31, 2023; Project and Facilities Management (Robert Gilliam, Chief of Project Management, 387-5000) on January 26, 2023; Finance (Paul Garcia, Administrative Analyst, 386-8392 and Penelope Chang, Administrative Analyst, 387-5285) on February 15, 2023; and County Finance and Administration (Valerie Clay, Deputy Executive Officer, 387-5423) on February 15, 2023.
(VT:361-8786)