REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
September 23, 2025
FROM
ENSEN MASON, Auditor-Controller/Treasurer/Tax Collector
SUBJECT
Title
Amendment to Contract with Grant Street Group to Defer Specified Requirements and Payments for the Property Tax Legacy Systems Replacement Project
End
RECOMMENDATION(S)
Recommendation
Approve Amendment No. 1 to Contract No. 22-359 with Grant Street Group, Inc. to revise the Statement of Work, defer specified requirements and related payments, and replace the Fee Schedule, reducing the total contract amount by $400,056 from $58,013,819 to $57,613,763 with no change to the contract term of May 24, 2022, through June 30, 2032.
(Presenter: Ensen Mason, Auditor-Controller/Treasurer/Tax Collector, 382-7000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally Responsible and Business-Like Manner.
FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The amendment reduces the contract by $400,056 through credits for the public Geographic Information System (GIS) Dashboard and Tableau licensing, as the County will develop its own dashboard and purchase Tableau licenses directly and defers $5,000,000 in payments to December 2025 and July 2026 to align with future milestones. Sufficient appropriation has been included in the Auditor-Controller/Treasurer/Tax Collector's (ATC) 2025-26 budget and will be included in the 2026-27 recommended budget.
BACKGROUND INFORMATION
On May 24, 2022 (Item No. 25), the Board of Supervisors approved Contract No. 22-359 with Grant Street Group (GSG) as part of the Property Tax Legacy Systems Replacement (PTLSR) Project for a modernized County property tax system (TaxSys) in the amount of $58,013,819 for the total contract period of May 24, 2022, through June 30, 2032.
On July 14, 2025, AT...