REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF BOARD GOVERNED COUNTY SERVICE AREAS
AND RECORD OF ACTION
August 5, 2025
FROM
NOEL CASTILLO, Director, Department of Public Works - Special Districts
SUBJECT
Title
Capital Improvement Program Project for County Service Area 70 J Oak Hills Chromium-6 Treatment Project
End
RECOMMENDATION(S)
Recommendation
Acting as the governing body of County Service Area 70 J Oak Hills:
1. Approve Capital Improvement Program Project, in the amount of $907,772, for the Chromium-6 Treatment Project.
2. Approve a professional engineering design and environmental services contract with Albert A. Webb & Associates, in the amount of $907,772, and for a term of August 5, 2025 through October 1, 2028, for the design of construction plans and specifications for the County Service Area 70 J Oak Hills Chromium-6 Treatment Project.
3. Authorize the Auditor-Controller/Treasurer/Tax Collector to post budget adjustments in the amount of $907,772, as detailed in the Financial Impact Section, for the County Service Area 70 J Oak Hills - Chromium-6 Treatment Project (Four votes required).
(Presenter: Noel Castillo, Director, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). Costs for the recommended professional engineering design and environmental services contract for County Service Area 70 J Oak Hills (District) Chromium-6 Treatment Project (Project) will be funded by the District's Available Unrestricted Net Position. The Department of Public Works - Special Districts (Department) anticipates returning to the Board of Supervisors (Board) at a later date with a recommendation to approve construction funding.
The following 2025-26 b...
Click here for full text