REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
August 22, 2023
FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation
SUBJECT
Title
Cooperative Agreement with City of Rialto for the Cactus Avenue and Easton Street Project in the Rialto Area
End
RECOMMENDATION(S)
Recommendation
1. Approve Cooperative Agreement with the City of Rialto, effective August 22, 2023 through December 31, 2028, or project completion/final payment for the Cactus Avenue and Easton Street Project in the Rialto area, whichever occurs first, wherein the County will contribute $665,000 and the City of Rialto will contribute $222,000 towards the estimated total cost of $887,000.
2. Authorize the Director of the Department of Public Works or Assistant Director of the Department of Public Works, to increase the County contribution amount up to 25 percent, from $665,000 to $831,250, should additional costs necessitate such an increase.
(Presenter: Brendon Biggs, Director, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The total estimated cost for the Cactus Avenue and Easton Street Project in the Rialto area (Project) is $887,000. The County's share of cost is estimated to be $665,000 and will be funded with Senate Bill 1 Road Maintenance and Rehabilitation Account (RMRA) funds. The remaining cost of the Project, estimated to be $222,000, will be funded by the City of Rialto (City). Sufficient appropriation and revenue for the Project are included in the Department of Public Works (Department) 2023-24 Road Operations budget and will be included in future recommended budgets (6650002000 H15228).
BACKGROUND INFORMATION
The Projec...