Subject: Final Environmental Impact Report and Environmental Assessment for the National Trails Highway at 10 Bridges Project
Attachments: 1. ATT-PW-TRANS-5-7-24-NTH_10_Bridges_SOC_FOF_2024-03-15_clean, 2. ADD-ATT-PW-TRans-05-07-24 National Trails Highway 10 Bridges MMRP 5954(142) FED 5.1.24, 3. Item #45 Executed BAI
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

May 7, 2024

FROM
NOEL CASTILLO, Director, Department of Public Works

SUBJECT
Title
Final Environmental Impact Report and Environmental Assessment for the National Trails Highway at 10 Bridges Project
End

RECOMMENDATION(S)
Recommendation
1. Certify that the Final Environmental Impact Report/Environmental Assessment (SCH No. 2021040231) for the National Trails Highway at 10 Bridges Project has been completed in compliance with the California Environmental Quality Act Guidelines that it has been reviewed and considered prior to approving the project, and that the report reflects the independent judgement of the Board of Supervisors.
2. Adopt the Findings of Fact and Statement of Overriding Considerations relating to the National Trails Highway at 10 Bridges Project Final Environmental Impact Report in compliance with the California Environmental Quality Act Guidelines.
3. Adopt the Mitigation Monitoring and Reporting Program for the National Trails Highway at 10 Bridges Project.
4. Direct the Department of Public Works to file the Notice of Determination in accordance with the California Environmental Quality Act.
(Presenter: Noel Castillo, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health, and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The Project is financed by Federal Highway Bridge Planning funds (88.53%) and Discretionary General Funds (11.47%) allocated to the Department of Public Works (Department) in the 2014-15 through 2016-17 and 2018-19 recommended budgets. The requested administrative actions have minimal financial impact. Sufficient revenue and appropriation are included in ...