File #: 10414   
Type: Consent Status: Passed
File created: 6/26/2024 Department: Public Works-Transportation
On agenda: 7/9/2024 Final action: 7/9/2024
Subject: Capital Improvement Program Project and Allocation of American Rescue Plan Act Funding for Summit Valley Road
Attachments: 1. MAP-PW-TRANS-7-9-2024 ARPA Funding for Summit Valley Road Traffic Control Devices
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

July 9, 2024

FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation

SUBJECT
Title
Capital Improvement Program Project and Allocation of American Rescue Plan Act Funding for Summit Valley Road
End

RECOMMENDATION(S)
Recommendation
1. Approve the Capital Improvement Program - Summit Valley Road Traffic Control Devices Project in the City of Hesperia and unincorporated Hesperia area in the amount of $600,000.
2. Approve the use of up to $600,000 of American Rescue Plan Act Coronavirus Local Fiscal Recovery Fund program funding for eligible costs for the Summit Valley Road Traffic Control Devices Project.
3. Authorize the Auditor-Controller/Treasurer/Tax Collector to post necessary budget adjustments, as detailed in the Financial Impact section, needed for the Summit Valley Road Traffic Control Devices Project (Four votes required).
(Presenter: Noel Castillo, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Provide for the Safety, Health and Social Service Needs of County Residents.
Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Summit Valley Road Traffic Control Devices Project in the City of Hesperia and unincorporated Hesperia area (Project) will be funded with the San Bernardino County (County) allocation of American Rescue Plan Act (ARPA) Coronavirus Local Fiscal Recovery Fund (Recovery Fund), which provides reimbursement of up to $600,000 for eligible costs for the Project. The following budget adjustments are necessary to establish the Department of Public Works' (Department) Project budget in the 2024-25 Road Operations budget (6650002000 H15255):

Fund Center
Commitment Item
Description
Action
Amount
6650002000
40509194
American Rescue Plan Act Re...