REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
April 8, 2025
FROM
DON DAY, Director, Project and Facilities Management Department
ANDREW GOLDFRACH, ARMC Chief Executive Officer, Arrowhead Regional Medical Center
SUBJECT
Title
Construction Contract with CDG Builders, Inc., for the ARMC Sterilization System Installation and ARMC Sonic Irrigation Replacements Projects in Colton
End
RECOMMENDATION(S)
Recommendation
1. Approve Addendum No. 1 to the bid documents for the ARMC Sterilization System Installation and ARMC Sonic Irrigation Replacements projects, dated January 6, 2025, providing clarification to contractors' questions and request for information and changing the bid opening date from January 20, 2025, to January 21, 2025.
2. Award construction contract to CDG Builders, Inc., in the amount of $1,164,150, for both the ARMC Sterilization System Installation and ARMC Sonic Irrigation Replacements projects in Colton.
3. Authorize the Director of Project and Facilities Management Department to order any necessary changes or additions in the work being performed under the contract, for a total not to exceed $70,707 pursuant to Public Contract Code Section 20142.
4. Authorize the Director of Project and Facilities Management Department to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Don Day, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve ARMC County Hospital Operations.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The contract award will be fully funded by both the ARMC Sterilization System Installation (WBSE 10.10.1142) and ARMC Sonic Irrigation Replacements (WBSE 10.10.1066) project budgets, totaling $6,088,736. This includes the project (collectively ref...
Click here for full text