Skip to main content
File #: 12353   
Type: Consent Status: Passed
File created: 6/2/2025 Department: Public Works-Transportation
On agenda: 6/10/2025 Final action: 6/10/2025
Subject: Contract with Dokken Engineering for Professional Engineering, Environmental Services and Construction Support for the Replacement of 30 Bridges on National Trails Highway at Various Locations
Attachments: 1. ADD-CON-PW-Trans 6-10-2025 Dokken Contract National Trails Highway 30 Bridges
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

June 10, 2025

FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation

SUBJECT
Title
Contract with Dokken Engineering for Professional Engineering, Environmental Services and Construction Support for the Replacement of 30 Bridges on National Trails Highway at Various Locations
End

RECOMMENDATION(S)
Recommendation
1. Approve Contract with Dokken Engineering to provide professional engineering, environmental services and construction support for the Replacement of 30 Bridges on National Trails Highway at various locations, in the amount not-to-exceed $7,134,805.61, for a term of five years, from June 10, 2025 through June 10, 2030, with the option to extend the contract term for up to two additional one-year terms, by mutual agreement of the parties.
2. Authorize the Director of the Department of Public Works to execute the contract extensions set forth in Recommendation No. 1 on behalf of the County, subject to County Counsel review.
3. Direct the Director of the Department of Public Works to transmit any approved contract extensions to the Clerk of the Board of Supervisors within 30 days of execution.
(Presenter: Noel Castillo, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The costs for the design phase of the replacement of 30 bridges on National Trails Highway in various locations (Project) will be funded with 50% Local Partnership Program (LPP) funds administered by San Bernardino County Transportation Authority (SBCTA) and a 50% local match funded with Discretionary General Funding (DGF) allocated to the Department of Pub...

Click here for full text