REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
December 14, 2021
FROM
TERRY W. THOMPSON, Director, Real Estate Services Department - Project Management
SUBJECT
Title
Amendment to Construction Contract with Jergensen Construction, Inc. for the 800 MHz Sunset - Generator Replacement Project
End
RECOMMENDATION
Recommendation
Approve Amendment No. 1 to Contract No. 21-315 with Jergensen Construction, Inc., increasing the Contract total by $6,351, from $130,000 to a total of $136,351, and extending the Contract Time by an additional 91 calendar days, from 210 calendar days to 301 calendar days, with a new construction completion date of April 4, 2022, for the 800 MHz Sunset - Generator Replacement Project (WBSE 10.10.0993) located in the City of Redlands (Assessor Parcel Number 030045108) (Four votes required).
(Presenter: Terry W. Thompson, Director, 387-5000)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of Amendment No. 1 will not result in the use of additional Discretionary General Funding (Net County Cost). The 800 MHz Sunset - Generator Replacement Project (Project) budget of $726,302 (WBSE 10.10.0993) is funded with Discretionary General Funding, previously approved by the Board of Supervisors (Board) as part of the 2011-12 Capital Improvement Program (CIP) Countywide 800 MHz Radio System Upgrade Project and is comprised of the following:
|
Description |
Amount |
|
Investigation and Assessment |
$ 30,000 |
|
Design |
$ 76,760 |
|
Testing/Inspection |
$ 2,000 |
|
Project Management |
$ 40,000 |
|
Construction |
$136,351 |
|
Construction Contingency |
$ 13,000 |
|
Project Contingency |
$428,191 |
|
Total Project Budget |
$726,302 |
BACKGROUND INFORMATION
On November 17, 2020 (Item No. 76), the Board authorized the Real Estate Services - Project Management to advertise for competitive bids for the Project. On May 4, 2021 (Item No. 52), the Board awarded a construction contract to Jergensen Construction Inc. (Jergensen) for the Project.
Amendment No. 1 will increase the contract amount by $6,351 with Jergensen for the additional labor, materials and equipment required to install a new 200-amp meter can with main breaker per Southern California Edison (SCE) requirements and remove existing meter can and conduit on the load side of the electrical service per Change Order Request (COR) No. 001 dated September 29, 2021. The additional scope of work was unforeseen and is required by Southern California Edison.
Amendment No. 1 will also extend the Contract Time with Jergensen an additional 91 calendar days, from 210 calendar days to 301 calendar days, to accommodate the additional work required by SCE, as well as material shortages caused by the COVID-19 pandemic. The Contract Time is the agreed upon period of time allotted to Jergensen to achieve completion of the entire scope of work without the imposition of liquidated damages. Extension of the Contract Time is permitted by Section 3.1 of the contract, subject to written approval of the County. At all times the contract as a whole remains in full force and effect until all issues related to the contract have been resolved. The original construction completion date was January 3, 2022; the new construction completion date is April 4, 2022.
PROCUREMENT
The unanticipated additional cost described above is related to events that took place after the competitive bid process that resulted in the original contract with Jergensen. Therefore, no additional procurement activities are required. Purchasing supports the continued use of Jergensen for this project.
Per Public Contract Code section 20136, Board approval is required for this amendment to the contract with Jergensen. Purchasing supports the continued use of Jergensen for this project.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Katherine Hardy, Deputy County Counsel, 387-5455) on October, 29, 2021; Innovation and Technology Department (Tim Trager, Chief, Public Safety Communications Division, 388-5563) on November 2, 2021; Purchasing Department (Bruce Cole, Supervising Buyer, 387-2148) on November 3, 2021; Real Estate Services - Project Management (Kevin Ryan, Assistant Director, 387-5000) on November 10, 2021; Real Estate Services Department (Jennifer Costa, Assistant Director, 387-5000) on November 10, 2021; Finance (Wen Mai, Principal Administrative Analyst, 387-4020) on November 23, 2021; and County Finance and Administration (Diana Atkeson, Deputy Executive Officer, 387-5423) on November 23, 2021.
(EG: 329-0165)