Legislation Details

File #: 7843   
Type: Consent Status: Passed
File created: 4/17/2023 Department: Bloomington Recreation and Park District
On agenda: 4/25/2023 Final action: 4/25/2023
Subject: Various Actions for the Kessler Park Corridor Project and the Kessler Park Wi-Fi Project in Bloomington
Attachments: 1. ADD-ATT-BRPD-042523-Kessler Corridor Section C - Prevailing Wages 3 of 10, 2. ADD-ATT-BRPD-042523-Kessler Corridor Section D - General Conditions 4 of 10, 3. ADD-ATT-BRPD-042523-Kessler Corridor Section E - Special Conditions 5 of 10, 4. ADD-ATT-BRPD-042523-Kessler Corridor Section F - Technical Specifications 6 of 10, 5. ADD-ATT-BRPD-042523-Kessler Corridor Section G - Contract Drawings Part 1 7 of 10, 6. ADD-ATT-BRPD-042523-Kessler Corridor Section G - Contract Drawings Part 2 8 of 10, 7. ADD-ATT-BRPD-042523-Kessler Corridor Section G - Contract Drawings Part 3 9 of 10, 8. ADD-ATT-BRPD-042523-Kessler Corridor Section H - Geotech Report 10 of 10, 9. ADD-ATT-BRPD-042523-Kessler Corridor Section A - Bidding Requirements 1 of 10, 10. ADD-ATT-BRPD-042523-Kessler Corridor Section B - Contract and Bonds 2 of 10, 11. R1-ATT-BRPD-042523 Kessler Park Corridor NOE, 12. R1-ATT-BRPD-042523 Kessler Park Corridor NOE, 13. Item #67 Executed BAI

REPORT/RECOMMENDATION TO THE BOARD OF DIRECTORS

OF BLOOMINGTON RECREATION AND PARK DISTRICT

AND RECORD OF ACTION

 

April 25, 2023

 

FROM

BRENDON BIGGS, Director, Department of Public Works - Special Districts

         

SUBJECT                      

Title                     

Various Actions for the Kessler Park Corridor Project and the Kessler Park Wi-Fi Project in Bloomington

End

 

RECOMMENDATION(S)

Recommendation

Acting as the governing body of Bloomington Recreation and Park District:

1.                     Find that the Kessler Park Corridor Project and the Kessler Park Wi-Fi Project are exempt under the California Environmental Quality Act, Title 14 of the California Code of Regulations Section 15301(a) Class 1 (alteration of existing facilities). 

2.                     Approve the Kessler Park Corridor Project and the Kessler Park Wi-Fi Project, as defined in the Notice of Exemption.

3.                     Approve the plans and specifications for the Kessler Park Corridor Project and the Kessler Park Wi-Fi Project.

4.                     Authorize the Director of the Department of Public Works to advertise the Kessler Park Corridor Project and the Kessler Park Wi-Fi Project for competitive bids.

5.                     Direct the Secretary of the Board of Directors to file and post the Notice of Exemption.

(Presenter: Brendon Biggs, Director, 387-7906)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Operate in a Fiscally-Responsible and Business-Like Manner.

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Kessler Park Corridor Project will be funded through the Capital Improvement Program (CIP) of the Bloomington Recreation and Park District (District). The Kessler Park Wi-Fi Project will be funded through a portion of the $518,576 allocation of American Rescue Plan Act funding approved by the Board of Directors (Board) on February 28, 2023 (Item No. 72).  Sufficient appropriation for these projects is included in the District’s 2022-23 budget, and will be included in future recommended budgets as needed.

 

BACKGROUND INFORMATION

The District was established by an act of the San Bernardino County Board of Supervisors on July 19, 1972. The District maintains two community parks (Ayala Park and Kessler Park), an equestrian arena, sports fields, and a community center that offer various recreational activities for the community of Bloomington.

 

This item is comprised of the two capital improvement projects (collectively referred to as the Project) at Kessler Park (Park) in Bloomington. The first is the Kessler Park Corridor project, which consists of constructing interior concrete between the four ball fields to improve visual appeal, improve recreation opportunities for children, and reduce windblown dust at the Park. The second is the Kessler Park Wi-Fi project, which consists of constructing a high speed fiberoptic line to the site and installing a Wi-Fi main hub system with access points places around the Park, thus providing high speed internet access to local residents.

 

The Department of Public Works - Special Districts (Department) staff reviewed the Project and determined that a categorical exemption in accordance with the California Environmental Quality Act (CEQA) Guidelines, Title 14 of the California Code of Regulations, Section 15301(a) Class 1 is appropriate.  The Class 1 exemption allows for alteration activities on existing and similar facilities, including publicly owned facilities that involve negligible or no expansion of use beyond that existing at the time of the lead agency’s determination.  When the Board considers the environmental finding, the filing and posting of a Notice of Exemption is recommended.

 

In addition to the CEQA finding, this item seeks Board approval of the Project’s plans and specifications and authorization to advertise for bids. Because work for the Kessler Park Wi-Fi Project will require coordination with the Kessler Park Corridor Project, the plans and specifications have been combined to ensure proper coordination and cost savings.

 

PROCUREMENT

The Project will be advertised for formal bids in accordance with Section 22037 of the California Public Contract Code. The Department anticipates returning to the Board in July 2023 with a recommendation for award of the Project’s construction contract.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Aaron Gest, Deputy County Counsel, 387-5455) on March 31, 2023; Finance (Tom Forster, Administrative Analyst, 387-4635) on April 5, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on April 10, 2023.