REPORT/RECOMMENDATION TO THE BOARD OF DIRECTORS
OF BLOOMINGTON RECREATION AND PARK DISTRICT
AND RECORD OF ACTION
April 25, 2023
FROM
BRENDON BIGGS, Director, Department of Public Works - Special Districts
SUBJECT
Title
Various Actions for the Kessler Park Corridor Project and the Kessler Park Wi-Fi Project in Bloomington
End
RECOMMENDATION(S)
Recommendation
Acting as the governing body of Bloomington Recreation and Park District:
1. Find that the Kessler Park Corridor Project and the Kessler Park Wi-Fi Project are exempt under the California Environmental Quality Act, Title 14 of the California Code of Regulations Section 15301(a) Class 1 (alteration of existing facilities).
2. Approve the Kessler Park Corridor Project and the Kessler Park Wi-Fi Project, as defined in the Notice of Exemption.
3. Approve the plans and specifications for the Kessler Park Corridor Project and the Kessler Park Wi-Fi Project.
4. Authorize the Director of the Department of Public Works to advertise the Kessler Park Corridor Project and the Kessler Park Wi-Fi Project for competitive bids.
5. Direct the Secretary of the Board of Directors to file and post the Notice of Exemption.
(Presenter: Brendon Biggs, Director, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Kessler Park Corridor Project will be funded through the Capital Improvement Program (CIP) of the Bloomington Recreation and Park District (District). The Kessler Park Wi-Fi Project will be funded through a portion of the $518,576 allocation of American Rescue Plan Act funding approved by the Board of Directors (Board) on February 28, 2023 (Item No. 72). Sufficient appropriation for these projects is included in the District’s 2022-23 budget, and will be included in future recommended budgets as needed.
BACKGROUND INFORMATION
The District was established by an act of the San Bernardino County Board of Supervisors on July 19, 1972. The District maintains two community parks (Ayala Park and Kessler Park), an equestrian arena, sports fields, and a community center that offer various recreational activities for the community of Bloomington.
This item is comprised of the two capital improvement projects (collectively referred to as the Project) at Kessler Park (Park) in Bloomington. The first is the Kessler Park Corridor project, which consists of constructing interior concrete between the four ball fields to improve visual appeal, improve recreation opportunities for children, and reduce windblown dust at the Park. The second is the Kessler Park Wi-Fi project, which consists of constructing a high speed fiberoptic line to the site and installing a Wi-Fi main hub system with access points places around the Park, thus providing high speed internet access to local residents.
The Department of Public Works - Special Districts (Department) staff reviewed the Project and determined that a categorical exemption in accordance with the California Environmental Quality Act (CEQA) Guidelines, Title 14 of the California Code of Regulations, Section 15301(a) Class 1 is appropriate. The Class 1 exemption allows for alteration activities on existing and similar facilities, including publicly owned facilities that involve negligible or no expansion of use beyond that existing at the time of the lead agency’s determination. When the Board considers the environmental finding, the filing and posting of a Notice of Exemption is recommended.
In addition to the CEQA finding, this item seeks Board approval of the Project’s plans and specifications and authorization to advertise for bids. Because work for the Kessler Park Wi-Fi Project will require coordination with the Kessler Park Corridor Project, the plans and specifications have been combined to ensure proper coordination and cost savings.
PROCUREMENT
The Project will be advertised for formal bids in accordance with Section 22037 of the California Public Contract Code. The Department anticipates returning to the Board in July 2023 with a recommendation for award of the Project’s construction contract.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Aaron Gest, Deputy County Counsel, 387-5455) on March 31, 2023; Finance (Tom Forster, Administrative Analyst, 387-4635) on April 5, 2023; and County Finance and Administration (Paloma Hernandez-Barker, Deputy Executive Officer, 387-5423) on April 10, 2023.