Skip to main content
File #: 13764   
Type: Consent Status: Passed
File created: 3/2/2026 Department: San Bernardino County Flood Control District
On agenda: 3/10/2026 Final action: 3/10/2026
Subject: Contract with Albert A. Webb Associates for Professional Civil Engineering Services for the Comprehensive Storm Drain Plan 3-4 and Design of El Rivino Basin and Outlet Storm Drain.
Attachments: 1. ADD-CON-FCD 3-10-26 Con with Albert A Webb for CSDP 3-4 Design of El Rivino Basin, 2. ADD-EXH-FCD 3-10-26 Exhibit 1 - Scope of Work, 3. ADD-EXH-FCD 3-10-26 Exhibit 2 - Fee Schedule, 4. ADD-EXH-FCD 3-10-26 Exhibit 3 - FEMA Grant Documents, 5. Item #54 Executed BAI, 6. 26-150 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY FLOOD CONTROL DISTRICT
AND RECORD OF ACTION

March 10, 2026

FROM
NOEL CASTILLO, Chief Flood Control Engineer, Flood Control District

SUBJECT
Title
Contract with Albert A. Webb Associates for Professional Civil Engineering Services for the Comprehensive Storm Drain Plan 3-4 and Design of El Rivino Basin and Outlet Storm Drain.
End

RECOMMENDATION(S)
Recommendation
Acting as the governing body of the San Bernardino County Flood Control District:
1. Approve Contract with Albert A. Webb Associates, to provide professional civil engineering services for the Comprehensive Storm Drain Plan 3-4 and El Rivino Basin and Outlet Storm Drain, in the amount not to exceed $1,438,000, for the period of March 16, 2026 to March 15, 2029.
2. Authorize the Chief Flood Control Engineer or Engineering Manager to add and/or delete services and reallocate funding between tasks as required to complete the work outlined in the Contract in Recommendation No. 1 without increasing the total cost or changing the term of the Contract, subject to review by County Counsel.
(Presenter: Noel Castillo, Chief Flood Control Engineer, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Promote and Fulfill the Countywide Vision.
Provide for the Safety, Health and Social Service Needs of County Residents.
Operate in a Fiscally-Responsible and Business-Like Manner.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). Funding for the Comprehensive Storm Drain Plan (CSDP) 3-4 and Design of El Rivino Basin and Outlet Storm Drain (Line D) includes Hazard Mitigation Grant Program funds awarded by the U.S. Department of Homeland Security, Federal Emergency Management Agency at a 75% cost share, and the San Bernardino County Flood Control District (District) for the remaining 25% cost share. The District's 25% cost share is funded...

Click here for full text