San Bernardino header
File #: 10944   
Type: Consent Status: Passed
File created: 9/27/2024 Department: Public Works-Transportation
On agenda: 10/8/2024 Final action: 10/8/2024
Subject: Ratification of Final Application Submitted to the Federal Railroad Administration for the Consolidated Railroad Infrastructure and Safety Improvements Grant
Attachments: 1. MAP-PW-Trans 10-8-24 CRISI Grant Application Ratification, 2. ADD-ATT-PW-Trans-10-8-24 CRISI Grant Application Ratification, 3. Item #30 Executed BAI
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

October 8, 2024

FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation

SUBJECT
Title
Ratification of Final Application Submitted to the Federal Railroad Administration for the Consolidated Railroad Infrastructure and Safety Improvements Grant
End

RECOMMENDATION(S)
Recommendation
Ratify the approval of final grant application submitted to the Federal Railroad Administration, in the amount of $40,000,000, for Consolidated Railroad Infrastructure and Safety Improvements grant call-for-projects to construct a grade separation and mobility infrastructure project for Vista Road in the Helendale area.
(Presenter: Noel Castillo, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Ensure Development of a Well-Planned, Balanced, and Sustainable County.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Department of Public Works (Department) is requesting ratification of a final grant application for the Consolidated Railroad Infrastructure and Safety Improvements (CRISI) grant applications submitted to the Federal Railroad Administration requesting $40,000,000 towards the $50,000,000 total construction cost to construct a grade separation (Project) for Vista Road in the Helendale area. Pursuant to the terms of the CRISI grant, the County is required to provide a 20 percent local match of $10,000,000 which is anticipated to be funded by the Burlington Northern Santa Fe (BNSF) Railroad. If the CRISI grant is awarded, the Department will present an item to the Board of Supervisors (Board) to accept the award and will work with BNSF Railroad to bring a funding agreement before the Board for the 20 percent local match requirement of $10,000,000.

BACKGROUND INFORMATION
The proposed Project, for w...