Skip to main content
File #: 13152   
Type: Consent Status: Agenda Ready
File created: 11/5/2025 Department: Project and Facilities Management
On agenda: 11/18/2025 Final action:
Subject: Budget Adjustment and Construction Contract with ACCO Engineered Systems, Inc., for the Arrowhead Regional Medical Center Cooling Tower Replacement Project
Attachments: 1. ATT-PFMD-111825-Bid Tabulation ARMC Cooling Tower Replacement, 2. ATT-PFMD-111825-ACCO Engineering Bid- ARMC Cooling Tower Replacement, 3. ATT-PFMD-111825-Addendum 1 ARMC Cooling Tower Replacement, 4. ATT-PFMD-111825-Addendum 2 ARMC Cooling Tower Replacement, 5. R1-CON-PFMD-111825-Construction Contract ARMC Cooling Tower Replacement
Date Action ByActionResultAction DetailsAgenda DocumentsVideo
No records to display.
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

November 18, 2025

FROM
DON DAY, Director, Project and Facilities Management Department
ANDREW GOLDFRACH, ARMC Chief Executive Officer, Arrowhead Regional Medical Center

SUBJECT
Title
Budget Adjustment and Construction Contract with ACCO Engineered Systems, Inc., for the Arrowhead Regional Medical Center Cooling Tower Replacement Project
End

RECOMMENDATION(S)
Recommendation
1. Approve the following addenda to the bid documents for the Arrowhead Regional Medical Center Cooling Tower Replacement Project:
a. Addendum No. 1, dated July 31, 2025, to the bid documents, which revised the bid opening date.
b. Addendum No. 2, dated August 5, 2025, to the bid documents, which provided answers to pre-bid questions, and modified plans and specification documents.
2. Award Construction Contract, in the amount of $10,641,888, to ACCO Engineered Systems, Inc., for a contract period of 450 calendar days from the date of the issuance of the Notice to Proceed, for the Arrowhead Regional Medical Center Cooling Tower Replacement Project in Colton.
3. Authorize the Director of the Project and Facilities Management Department to order any necessary changes or additions in the work being performed under the contract, for a total not to exceed $210,000, pursuant to Public Contract Code Section 20142.
4. Authorize the Director of Project and Facilities Management Department to accept the work when 100% complete and execute and file the Notice of Completion.
5. Approve a budget increase in the amount of $2,272,425 to Capital Improvement Program Project No. 21-047, increasing the total project budget from $11,256,150 to $13,528,575, for the Arrowhead Regional Medical Center Cooling Tower Replacement Project.
6. Authorize the Auditor-Controller/Treasure/Tax Collector to post necessary budget adjustments, as detailed in the Financial Impact section (Four votes required).
(Present...

Click here for full text