Subject: Contract with KEC Engineering Corporation Mission Zanja Bridge Project on the Santa Ana River Trail in the San Bernardino Area
Attachments: 1. CON-PW-Trans&Parks 11-19-24 Con with KEC Engineering for Mission Zanja Bridge, San Bernardino Area, 2. ATT-PW-Trans&Parks 11-19-24 Con with KEC Engineering for Mission Zanja Bridge, San Bernardino Area, Addendum No. 1, 3. MAP-PW-Trans&Parks 11-19-24 Con with KEC Engineering for Mission Zanja Bridge, San Bernardino Area, 4. ATT-PW-Trans&Parks 11-19-24 Con with KEC Engineering for Mission Zanja Bridge, San Bernardino Area, Addendum No. 4, 5. ATT-PW-Trans&Parks 11-19-24 Con with KEC Engineering for Mission Zanja Bridge, San Bernardino Area, Addendum No. 3, 6. ATT-PW-Trans&Parks 11-19-24 Con with KEC Engineering for Mission Zanja Bridge, San Bernardino Area, Addendum No. 2, 7. Item #49 Executed BAI, 8. 24-1087 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

November 19, 2024

FROM
NOEL CASTILLO, Director, Department of Public Works - Transportation
BEAHTA DAVIS, Director, Regional Parks Department

SUBJECT
Title
Contract with KEC Engineering Corporation Mission Zanja Bridge Project on the Santa Ana River Trail in the San Bernardino Area
End

RECOMMENDATION(S)
Recommendation
1. Approve Addendum No. 1, issued on August 26, 2024, Addendum No. 2, issued on September 4, 2024, Addendum No. 3, issued on September 12, 2024, and Addendum No. 4, issued on September 20, 2024, to the bid documents for the Mission Zanja Bridge Project on the Santa Ana River Trail in the San Bernardino area.
2. Award a construction contract to KEC Engineering Corporation (Corona, CA) in the amount of $2,473,897.22 for the Mission Zanja Bridge Project on the Santa Ana River Trail in the San Bernardino area.
3. Authorize a contingency fund of $247,389 for the Santa Ana River Trail in the San Bernardino area.
4. Authorize the Director of the Department of Public Works to approve the expenditure of the contingency fund of $247,389 for verified quantity overruns for this unit priced construction contract.
5. Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the contract for a total amount not to exceed $136,194 of the $247,389 contingency fund, pursuant to Public Contract Code section 20142.
6. Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.
7. Authorize an allocation of $2,407,856 from the Community Service Upgrades General Fund Reserve for the Mission Zanja Bridge Project over the Santa Ana River Trail in the San Bernardino area for the increased cost in construction, construction engineering, and construction contingency.
8. Authorize the Auditor-Controller/Treasurer/Tax Co...