File #: 13802   
Type: Consent Status: Agenda Ready
File created: 3/12/2026 Department: Bloomington Recreation and Park District
On agenda: 3/24/2026 Final action:
Subject: Amendment to Contract with KTU&A for the Kessler Park Master Plan Phase 1 Project
Attachments: 1. CON-BRPD-032426 KTU&A - Amendment No.pdf
Date Action ByActionResultAction DetailsAgenda DocumentsVideo
No records to display.
REPORT/RECOMMENDATION TO THE BOARD OF DIRECTORS
OF BLOOMINGTON RECREATION AND PARK DISTRICT
AND RECORD OF ACTION

March 24, 2026

FROM
NOEL CASTILLO, Director, Department of Public Works - Special Districts

SUBJECT
Title
Amendment to Contract with KTU&A for the Kessler Park Master Plan Phase 1 Project
End

RECOMMENDATION(S)
Recommendation
Approve Amendment No. 1 to Contract No. 24-950 with KTU&A, for professional engineering design services associated with the Kessler Park Master Plan Phase 1 Project, increasing the total approved contract amount by $225,908, from $851,692 to $1,077,600, for additional design services for the added Dream Field II scope of work, with no change to the contract term of September 24, 2024 through September 24, 2029.
(Presenter: Noel Castillo, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). Funding for the Kessler Park Master Plan Phase I Project (Project) was approved by the Board of Supervisors (Board) on September 24, 2024 (Item No. 84) from Discretionary General Funding in the amount of $5,780,700 and funded by General Fund Contingencies. Amendment No. 1 to KTU&A Contract No. 24-950 (Contract) for the Project will be funded by available funds allocated by the Board for the Project. Sufficient appropriation and revenue are included in the 2025-26 budget to the Bloomington Recreation and Park District's (District) Capital Improvement Program (CIP) Project Number 30.30.0185.

BACKGROUND INFORMATION
The District maintains two community parks (Ayala Park and Kessler Park), an equestrian arena, sports fields, and a community center that offers various recreational activities for the community of Bloomington. The De...