REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION
December 15, 2020
FROM
TERRY W. THOMPSON, Director, Real Estate Services Department - Project Management
SUBJECT
Title
Award a Construction Contract to KASA Construction Inc., for the Yucaipa Regional Park RV Camping Modular Shower/Restroom Project
End
RECOMMENDATION(S)
Recommendation
1. Approve Addendum No. 1 to the bid documents dated November 19, 2020, which provided (1) revised Instructions to Bidders and revised Bid Proposal, (2) a construction estimate of $409,000, (3) clarifications to the Bid Documents, (4) changes to the Drawings, and (5) clarification to contractor questions for the Yucaipa Regional Park RV Camping Modular Shower/Restroom Project.
2. Award a construction contract in the amount of $318,500 to KASA Construction Inc., for a contract period of 90 calendar days from the date of the issuance of the Notice to Proceed, for the Yucaipa Regional Park RV Camping Modular Shower/Restroom Project.
3. Authorize the Director of the Real Estate Services Department to order any necessary changes or additions in the work being performed under the contract for a total amount not to exceed $28,425, pursuant to Public Contract Code Section 20142.
4. Authorize the Director of the Real Estate Services Department to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Terry W. Thompson, Director, 387-5252)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally-Responsible and Business-Like Manner.
FINANCIAL IMPACT
This item will not result in the use of Discretionary General Funding (Net County Cost). The Yucaipa Regional Park RV Camping Modular Shower/Restroom Project (Project) budget of $950,000 is comprised of the following components:
|
Project Design |
$39,000 |
|
Project Management, Inspection and Testing |
$197,686 |
|
Construction |
$318,500 |
|
Construction Contingency |
$31,850 |
|
Modular Shower Restrooms |
$267,964 |
|
Project Contingency |
$95,000 |
|
Total Project Budget |
$950,000 |
The Project budget of $950,000 is funded from the Community Development Block Grant Fund. Sufficient appropriation and revenue is included in the 2020-21 Capital Improvement Program (CIP) budget to award this contract.
BACKGROUND INFORMATION
The recommended item will award a construction contract for the Project. The Project will install two new owner furnished modular prefabricated shower restroom buildings, and includes civil site work, infrastructure utilities, and accessible path of travel from parking lot and recreational parking camp site for Yucaipa Regional Park. Additional amenities and increased accessibility provides for an improved experience for the public thereby meeting the County goals of Improving County Government Operations, and Operating in a Fiscally-Responsible and Business-Like Manner.
On October 27, 2020 (Item No. 79), the Board of Supervisors (Board) found the Project to be categorically exempt from further review under Section 15301 (a)(c)(d) (Existing Facilities) and Section 15302 (b) (Replacement or Reconstruction) of the California Environmental Quality Act Guidelines (CEQA) (Title 14, California Code of Regulations). As evidenced by the Notice of Exemption, Section 15301 provides categorical exemption for projects involving minor alteration of Class 1 Existing Facilities with no or negligible expansion of use. Subsections (a), (c) and (d) include project elements related to the exterior Americans with Disabilities Act (ADA) alterations.
This Project is consistent with County Administrative Office approved CIP request No. 21-093.
PROCUREMENT
On October 27, 2020 (Item No. 79), the Board authorized the Real Estate Services Department - Project Management (RESD-PM) to advertise for competitive bids. RESD-PM advertised for bids in the Daily Press on October 30, 2020, six Plan Rooms and on the County Electronic Procurement Network (ePro). On November 10, 2020, 20 contractors attended a mandatory job walk. On November 19, 2020, Addendum No. 1 was issued to provide (1) revised Instructions to Bidders and revised Bid Proposal, (2) a construction estimate of $409,000, (3) clarifications to the Bid Documents, (4) changes to the Drawings, and (5) clarification to contractor questions. On November 24, 2020, the following 11 bids were received:
|
Name |
Location |
Bid |
|
KASA Construction, Inc. |
Chino |
$318.500.00 |
|
Jergensen Construction, Inc. |
Oak Hills |
$335,600.00 |
|
Roadway Engineering & Contracting, Inc. |
Fontana |
$348,400.00 |
|
Three Peaks Corp |
Redlands |
$354,000.00 |
|
Dalke & Sons Construction, Inc. |
Riverside |
$378,890.00 |
|
RenewAge Energy Solutions |
El Segundo |
$379,614.30 |
|
C.S. Legacy Construction, Inc. |
Chino |
$383,216.00 |
|
Lifetime Industries Inc. dba Parkwest Construction Company |
Redlands |
$427,000.00 |
|
AToM Engineering Construction, Inc. |
Hemet |
$427,398.00 |
|
Los Angeles Engineering, Inc, |
Covina |
$494,000.00 |
|
Grandmaison Construction, Inc. |
Santa Clarita |
$511,000.00 |
PMD recommends the Board award the construction contract to KASA Construction Inc., the lowest responsive and responsible bidder.
REVIEW BY OTHERS
This item has been reviewed by County Counsel (Katherine Hardy, Deputy County Counsel, 387-5437) on November 30, 2020; Regional Parks Department (Beahta R. Davis, Director, Regional Parks Department) on November 30, 2020; Purchasing Department (Bruce Cole, Supervising Buyer, 387-2148) on November 30, 2020; Project Management Division (Don Day, Interim Deputy Director, 387-5000) on December 1, 2020; Real Estate Services Department (Jennifer Costa, Assistant Director, 387-5000) on November 30, 2020; Finance (Wen Mai, Principal Administrative Analyst, 387-4020) on December 1, 2020; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on December 1, 2020.