Subject: Contract with BKF Engineers for Design of Bandicoot Basin in the City of Hesperia
Attachments: 1. EXH-FCD 1-28-25 Contract with BKF Engineers for Design of Bandicoot Basin in the City of Hesperia Exhibit 1 Scope of Work, 2. EXH-FCD 1-28-25 Contract with BKF Engineers for Design of Bandicoot Basin in the City of Hesperia Exhibit 2 Fee Schedule, 3. R1-CON-FCD 1-28-25 Con with BKF Engineers Bandicoot Basin City of Hesperia, 4. Item #68 Executed BAI, 5. 25-86 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY FLOOD CONTROL DISTRICT
AND RECORD OF ACTION

January 28, 2025

FROM
Noel Castillo, Chief Flood Control Engineer, Flood Control District

SUBJECT
Title
Contract with BKF Engineers for Design of Bandicoot Basin in the City of Hesperia
End

RECOMMENDATION(S)
Recommendation
Acting as the governing body of the San Bernardino County Flood Control District:
1. Approve Contract with BKF Engineers to provide professional civil engineering services for the design of Bandicoot Basin, in the amount not to exceed $1,115,632, for a contract term of February 1, 2025, to January 31, 2028.
2. Authorize the Chief Flood Control Engineer or the Assistant Director to add and/or delete services and reallocate funding between tasks as required to complete the work outlined in the Contract without increasing the total Contract amount or changing the term of the Contract.
(Presenter: Noel Castillo, Chief Flood Control Engineer, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The San Bernardino County Flood Control District (District) is funded by property taxes, fee revenue, and other local, state and federal funding. The total contract amount of $1,115,632 is based on the fees outlined in the proposal presented by BKF Engineers, which includes government fees permits, and consultant services for time and materials. Sufficient appropriation and revenue have been included in the District's 2024-25 budget (1970002510) and will be included in future recommended budgets.

BACKGROUND INFORMATION
The Bandicoot Basin Project (Project) consists of the construction of a stormwater detention basin located within the City of Hesperia ...

Click here for full text