San Bernardino header
File #: 11179   
Type: Consent Status: Passed
File created: 11/8/2024 Department: Public Works-Special Districts
On agenda: 11/19/2024 Final action: 11/19/2024
Subject: Construction Contract for the Calico Ghost Town Regional Park - Bridge Replacement Project
Attachments: 1. ATT-PW-SD-111924 Calico Ghost Town - Addendum No. 1, 2. CON-PW-SD-111924-Contract Award to RE Schultz Construction, 3. ATT-PW-SD-1119124 Calico Ghost Town - Addendum No. 2, 4. ATT-PW-SD-111924 Calico Ghost Town - Addendum No. 5, 5. ATT-PW-SD-111924 Calico Ghost Town - Addendum No. 4, 6. ATT-PW-SD-111924 Calico Ghost Town - Addendum No. 3
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

November 19, 2024

FROM
NOEL CASTILLO, Director, Department of Public Works - Special Districts
BEAHTA R. DAVIS, Director, Regional Parks Department

SUBJECT
Title
Construction Contract for the Calico Ghost Town Regional Park - Bridge Replacement Project
End

RECOMMENDATION(S)
Recommendation
1. Approve Addendum No. 1 issued on August 13, 2024, Addendum No. 2 issued on August 14, 2024, Addendum No. 3 issued on September 4, 2024, Addendum No. 4 issued on September 4, 2024, and Addendum No. 5 issued on September 5, 2024, to the bid documents for the Calico Ghost Town Regional Park - Bridge Replacement Project.
2. Award construction contract to R.E. Schultz Construction, Inc., in the amount of $317,590 for the Calico Ghost Town Regional Park - Bridge Replacement Project.
3. Authorize a contingency fund of $19,228 for the Calico Ghost Town - Bridge Replacement Project.
4. Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the construction contract with R.E. Schultz Construction, Inc. for a total not-to-exceed $19,228 of the $19,228 contingency fund, pursuant to Public Contract Code Section 20142.
5. Authorize the Director of the Department of Public Works to accept the work when it is 100% complete and to execute and file the Notice of Completion.
(Presenter: Noel Castillo, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Ensure Development of a Well-Planned, Balanced, and Sustainable County.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). On September 12, 2023 (Item No. 60), the Board of Supervisors (Board) approved $368,538 from the Community Service Upgrades General Fund Reserve for the Calico ...

Click here for full text