File #: 11215   
Type: Consent Status: Passed
File created: 11/20/2024 Department: Project and Facilities Management
On agenda: 12/3/2024 Final action: 12/3/2024
Subject: Construction Contract with Wakeco, Inc., for the ARMC Sterilization System Installation - Mobile SPD Trailer Project in Colton
Attachments: 1. CON-PFMD-120324-Construction Contract-Wakeco, Inc.,-ARMC Sterilization System Installation–Mobile SPD Trailer Project, 2. Item #36 Executed BAI, 3. 24-1212 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

December 3, 2024

FROM
DON DAY, Director, Project and Facilities Management Department
ANDREW GOLDFRACH, ARMC Chief Executive Officer, Arrowhead Regional Medical Center

SUBJECT
Title
Construction Contract with Wakeco, Inc., for the ARMC Sterilization System Installation - Mobile SPD Trailer Project in Colton
End

RECOMMENDATION(S)
Recommendation
1. Award a construction contract, in the amount of $679,000, to Wakeco, Inc., for the ARMC Sterilization System Installation - Mobile SPD Trailer Project in Colton.
2. Authorize the Director of Project and Facilities Management Department to order any necessary changes or additions to the work being performed under the contract, for a total not to exceed $46,450 pursuant to Public Contract Code Section 20142.
3. Authorize the Director of Project and Facilities Management Department to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Don Day, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve ARMC County Hospital Operations.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The project budget of $5,212,983 is funded with ARMC Enterprise Funds. Sufficient appropriation and revenue are included in the 2024-25 Capital Improvement Program (CIP) budget to award this contract.

The Arrowhead Regional Medical Center (ARMC) Sterilization System Installation - Mobile SPD Trailer (Project) budget of $5,212,983 is comprised of the following components:

Description
Amount
Project Design
$ 181,940
Project Management, Inspection and Testing
$ 542,178
Construction
$ 3,801,072
Construction Contingency
$ 160,186
Project Contingency
$ 527,607
Total Project Budget
$ 5,...