REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY FLOOD CONTROL DISTRICT
AND RECORD OF ACTION
August 22, 2023
FROM
BRENDON BIGGS, Chief Flood Control Engineer, Flood Control District
SUBJECT
Title
Contract with KEC Engineering Corporation for the Randall Avenue Culvert Replacement Project at the Rialto Channel in the City of Rialto
End
RECOMMENDATION(S)
Recommendation
Acting as the governing body of the San Bernardino County Flood Control District:
1. Approve Addendum No. 1, issued on July 29, 2023, to the bid documents for the Randall Avenue Culvert Replacement Project at the Rialto Channel in the City of Rialto.
2. Award a contract to KEC Engineering Corporation (Corona, CA) in the amount of $2,383,383 for the Randall Avenue Culvert Replacement Project at the Rialto Channel in the City of Rialto.
3. Authorize a contingency fund of $238,338 for the Randall Avenue Culvert Replacement Project at the Rialto Channel in the City of Rialto.
4. Authorize the Chief Flood Control Engineer of the San Bernardino County Flood Control District to approve the expenditure of the contingency fund of $238,338 for verified quantity overruns for this unit priced construction contract.
5. Authorize the Chief Flood Control Engineer of the San Bernardino County Flood Control District to order any necessary changes or additions in the work being performed under the contract for a total amount not-to-exceed $131,669 of the $238,338 contingency fund, pursuant to Public Contract Code section 21061(d).
6. Authorize the Chief Flood Control Engineer of the San Bernardino County Flood Control District to accept the work when 100% complete and execute and file the Notice of Completion.
7. Authorize the Auditor-Controller/Treasurer/Tax Collector to post budget adjustments in the amount of $2,621,721, as detailed in the Financial Impact section, for the Randall Avenue Culvert Replacement Project at the Rialto Channel in the City of Rialto (Four votes require...