REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION
November 5, 2019
FROM
KEVIN BLAKESLEE, Director, Department of Public Works - Transportation
SUBJECT
Title
Measure "I" Five-Year Capital Project Needs Analysis and Project List for 2020-21 through 2024-25
End
RECOMMENDATION(S)
Recommendation
Adopt Resolution approving the Measure "I" Five-Year Valley Major Streets, Valley Freeway Interchange, and the Victor Valley Major Local Highways Programs Capital Project Needs Analysis project list for 2020-21 through 2024-25, identified in Exhibit "A" to the Resolution.
(Presenter: Mazin Kasey, Deputy Director, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Pursue County Goals and Objectives by Working with Other Agencies.
FINANCIAL IMPACT
Approval of the Measure "I" Five-Year Capital Project Needs Analysis (CPNA) project list will not result in the use of additional Discretionary General Funding (Net County Cost) or cost to the Department of Public Works (Department). The CPNA project list (attached to the resolution as "Exhibit A") identifies County of San Bernardino (County) projects eligible for Public Share reimbursement under the San Bernardino County Transportation Authority's (SBCTA) Valley Major Streets, Valley Freeway Interchange, and the Victor Valley Major Local Highways Programs, consistent with the SBCTA's Nexus Study and the County's Regional Transportation Development Mitigation Plan approved by the Board of Supervisors (Board) on December 5, 2006 (Item No. 57) and last updated on July 22, 2014 (Item No. 41). There is no financial impact to the County with the approval of this item.
BACKGROUND INFORMATION
Adoption of the resolution approves the annual update to the Measure "I" Five-Year CPNA project list for 2020-21 through 2024-25 (attached to the resolution as Exhibit "A"), which is comprised o...
Click here for full text