File #: 1440   
Type: Consent Status: Passed
File created: 12/9/2019 Department: Real Estate Services-Project Management Division
On agenda: 12/17/2019 Final action: 12/17/2019
Subject: V Amendment No. 1 to Construction Contract with Abboud Diamond Construction, Inc. for Onyx Peak Solar Upgrade Project
Attachments: 1. CON-RESD-PMD-121719-15-445 A-1 Abboud Diamond Construction, 2. Item #52 Executed BAI, 3. 18-755-A-1 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF THE COUNTY OF SAN BERNARDINO

AND RECORD OF ACTION

 

December 17, 2019

 

FROM

Terry W. Thompson, Director, Real Estate Services Department - Project Management Division 

         

SUBJECT                      

Title                     V

Amendment No. 1 to Construction Contract with Abboud Diamond Construction, Inc. for Onyx Peak Solar Upgrade Project

End

 

RECOMMENDATION(S)

Recommendation

1.                     Approve a $521,000 increase in the project budget, from $470,000 to $991,000, for the Onyx Peak Solar Upgrade Project (10.10.0175) located at Onyx Peak, Big Bear (APN 0305-201-05).

2.                     Approve Amendment No. 1 to Contract No. 15-445 with Diamond Construction, Inc. in the amount of $498,749 increasing the construction contract from $248,729 to a total of $747,478, and extending the contract end date from October 2, 2019 to April 10, 2020 for the Onyx Peak Solar Upgrade Project (10.10.0175) located at Onyx Peak, Big Bear (APN 0305-201-05) (Four Votes required).

3.                     Authorize the Auditor-Controller/Treasure/Tax Collector to adjust appropriation within the Capital Improvement Program (CIP), as detailed in the Financial Impact Section, transferring $521,000 from the 800 MHz Radio Replacement Project (10.10.0009) to the Onyx Peak Solar Upgrade Project (10.10.0175) increasing the total project budget from $470,000 to $991,000 (Four Votes required).

 (Presenter: Terry W. Thompson, Director, 387-5000)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Improve County Government Operations.

Provide for the Safety, Health and Social Service Needs of County Residents.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost).  The project budget of $991,000 is comprised of the following components:

 

Project Design

$40,000

Project Management, Inspection and Testing

$156,398

Construction

$747,478

Construction Contingency

$47,124

Total Project Budget

$991,000

 

The proposed funding source for the increase in the Project budget of $521,000 for the Onyx Peak Solar Upgrade Project (10.10.0175) is from the 800 MHz Radio Replacement Project (10.10.0009).  The revised total project budget of $991,000 is funded from Discretionary General Funding (Net County Cost) that is included in the overall budget for the 800 MHz Radio Replacement Project (10.10.0009) previously approved by the Board of Supervisors (Board) as part of the 2019-20 Capital Improvement Program (CIP). 

This item authorizes the Auditor-Controller/Treasurer/Tax Collector to post the following adjustments to the 2019-20 budgets:

 

Fund Center

WBSE

Commitment Item

Description

Action

Amount

7700003100

10.10.0175

54304030

Improvements to Structure

Increase

$521,000

7700003100

10.10.0175

40909995

Residual Equity Transfers In

Increase

$521,000

7700003100

10.10.0009

54304030

Improvements to Structure

Decrease

($521,000)

7700003100

10.10.0009

40909999

Residual Equity Transfers Out

Decrease

($521,000)

 

 

BACKGROUND INFORMATION

The Project located on APN 0305-201-05 in Big Bear will replace the existing failing solar panel array with higher capacity solar panels and add a second solar panel array to meet the increased electrical storage requirements, minimizing the need for emergency backup generator run time, thus satisfying the South Coast Air Quality Management District’s emergency generator run time permit parameters.  The upgrade to the Onyx Peak 800 MHz Antenna Site (Site) will provide reliable, cost effective electrical power to support the signal transmission from the Site to support County Fire, Sheriff, and Emergency Medical Responders thereby supporting the County and Chief Executive Officer Goals and Objectives of Improving County Government Operations.

 

Following the award of the construction contract to Abboud Diamond Construction, Inc. and prior to the start of construction, a fire destroyed an existing generator and shelter, which changed the scope of work for the Onyx Peak 800 MHz Antenna Site.  On June 11, 2019, IMEG Corp. the Engineer of Record released Bulletin No. 2 adding the replacement of the generator building, new slab, electrical, two propane tanks, and two new generators to the scope of work.  Amendment No. 1 will compensate Abboud Diamond Construction, Inc. for labor, materials, and equipment with the modifications to scope.

 

PROCUREMENT

The unanticipated additional cost items in this amendment are related to events that took place after the competitive bidding processes that resulted in the original contract with Abboud Diamond Construction, Inc.  Therefore, no additional procurement activities are required.

 

Per Public Contract Code sections 20136 and 20137, Board of Supervisors approval is required for this amendment and change order to the contract with Abboud Diamond Construction, Inc. 

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Katherine Hardy, Deputy County Counsel, 387-5437) on November 21, 2019; Purchasing Department (Michelle Churchill Buyer III, 387-2070) on November 22, 2019;  Project Management Division (Darlynn Wissert, Assistant Director, 387-5000) on November 22, 2019; Finance (Wen Mai, Principle Administrative Analyst, 387-4020) on December 2, 2019; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on December 2, 2019.

 