Attachments: 1. ATT-RESD-PMD-040720-Addendum No. 1-Drawings-Fleet Fuel Tank Infrastructure Phase II-10.10.0606_Part2, 2. ATT-RESD-PMD-040720-Addendum No. 1-Narrative-Fleet Fuel Tank Infrastructure Phase II-10.10.pdf, 3. ATT-RESD-PMD-040720-Addendum No. 1-Questions and Answers, 4. ATT-RESD-PMD-040720-Addendum No. 1-Drawings-Fleet Fuel Tank Infrastructure Phase II-10.10.0606, 5. ATT-RESD-PMD-040720-Addendum No. 1-Drawings-Fleet Fuel Tank Infrastructure Phase II-10.10.0606_Part1, 6. CON-RES-PMD-040720-Award Contract to Fleming for Fuel Tank Infrastructure Phase II - Baker Site, 7. Item #40 Executed BAI, 8. 20-181 Executed Contract

REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS

OF THE COUNTY OF SAN BERNARDINO

AND RECORD OF ACTION

 

April 7, 2020

 

FROM

Terry W. Thompson, Director, Real Estate Services Department - Project Management Division 

         

SUBJECT                      

Title                     v

Award Construction Contract to Fleming Environmental, Inc. for the Fuel Tank Infrastructure Phase II Project

End

 

RECOMMENDATION(S)

Recommendation

1.                     Approve the following addenda to the Bid Documents for the Fuel Tank Infrastructure Phase II Project (No. 10.10.0606).

a.                     Addendum No. 1 dated December 26, 2019, which provided clarifications in response to contractor questions and revised the Project drawings.

2.                     Award a construction contract in the amount of $627,894 to Fleming Environmental, Inc. of Fullerton, CA 92831 for the Fuel Tank Infrastructure Phase II Project.

3.                     Authorize the Director of Real Estate Services Department to order any necessary changes or additions in the work being performed under the contract for a total not to exceed $43,895, pursuant to Public Contract Code Section 20142.

4.                     Authorize the Director of Real Estate Services Department to accept the work when 100% complete, execute, and file the Notice of Completion.

(Presenter: Terry W. Thompson, Director, 387-5252)

Body

 

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES

Improve County Government Operations.

Operate in a Fiscally-Responsible and Business-Like Manner.

Ensure Development of a Well-Planned, Balanced, and Sustainable County.

 

FINANCIAL IMPACT

Approval of this item will not result in the use of Discretionary General Funding (Net County Cost).  The Fuel Tank Infrastructure Phase II Project (Project) budget of $1,000,000 is comprised of the following components:

 

Construction Management

$      71,901

Design

$      79,756

Labor Compliance

$      32,060

Materials Testing/ Inspection

$      65,600

Project Management

$      60,000

Construction

$    627,894

Construction Contingency

$      62,789

Total Project Budget

$ 1,000,000

 

The project budget of $1,000,000 is funded from the Fleet Management Department (Fleet) Internal Service Fund Net Position as approved by the Board of Supervisors (Board) as part of the 2019-20 Capital Improvement Program (CIP) First Quarter Budget Report.  Sufficient appropriation and revenue is included in the 2019-20 CIP budget to award this contract.

 

BACKGROUND INFORMATION

Approval of the recommendations will authorize the Real Estate Services Department (RESD), to proceed with this Project and construction of the Fleet fuel facility located in Baker.  The Project will install two 10,000 gallons fuel tanks, one with diesel fuel, and one with unleaded fuel adjacent to Fire Station #53 to Improve County Government Operations, and Ensure Development of a Well-Planned, Balanced, and Sustainable County.

 

On November 5, 2019 (Item No. 31), the Board found that this Project is exempt under California Environmental Quality Act Guidelines (CEQA) (Title 14, California Code of Regulations), Section 15301, Class 1, subsection (b), (Existing Facilities - Utility Addition) and directed the Clerk of the Board to file and post the Notice of Exemption for the Project.

 

This Project is consistent with County Administrative Office CIP request No. 18-183.

 

PROCUREMENT

On November 5, 2019 (Item No. 31), the Board authorized RESD to advertise for competitive bids for the Project.  On November 8, 2019, RESD advertised for bids in the Daily Press, six Plan Rooms, and on the County Electronic Procurement Network (ePro) website.  On December 3, 2019, five contractors attended a mandatory job walk.  On December 26, 2019, Addendum No. 1 was issued to provide clarifications to contractor questions and modified project drawings.  On January 8, 2020, the following bids were received:

 

Contractor

Location

Bid

Fleming Environmental, Inc.

Fullerton, CA

$ 627,894

Cora Constructors, Inc.

Palm Desert, CA

$ 770,000

 

RESD recommends the Board award the construction contract to Fleming Environmental, Inc., the lowest responsive and responsible bidder.

 

REVIEW BY OTHERS

This item has been reviewed by County Counsel (Katherine Hardy, Deputy County Counsel, 387-5437) on February 6, 2020; Fleet Management (Ron Lindsey, Director, 387-7870) on February 7, 2020; Purchasing Department (Cody Leslie, Buyer II, 387-2065) on February 13, 2020; Project Management (Jennifer Costa, Assistant Director, 387-5000) on February 14, 2020; Finance (Wen Mai, Principal Administrative Analyst, 387-4020 and Joon Cho, Administrative Analyst, 387-5142) on March 23, 2020; and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on March 24, 2020.

 