Subject: Cooperative Funding Agreement for the Santa Ana River Watershed Regional Water Quality Standards Task Force
Attachments: 1. ATT-FCD 6-2-20 Coop Funding Agr for SAR Watershed Water Quality Standards Task Force, 2. COV-FCD 6-2-20 Coop Funding Agr for SAR Watershed Water Quality Standards Task Force, 3. Item #45 Executed BAI, 4. 20-355 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE SAN BERNARDINO COUNTY FLOOD CONTROL DISTRICT
AND RECORD OF ACTION

June 2, 2020

FROM
BRENDON BIGGS, Interim Chief Flood Control Engineer, Flood Control District

SUBJECT
Title
Cooperative Funding Agreement for the Santa Ana River Watershed Regional Water Quality Standards Task Force
End

RECOMMENDATION(S)
Recommendation
Acting as the governing body of the San Bernardino County Flood Control District, approve the budgeted expenditure, in an amount not to exceed $165,225, for the period of July 1, 2020 through June 30, 2021, for administrative and technical services to support the Santa Ana River Watershed Regional Water Quality Standards Task Force in implementing requirements of the Santa Ana Regional Water Quality Control Board Basin Plan, per Agreement 16-949, Section 8, with the Santa Ana Watershed Project Authority.
(Presenter: Brendon Biggs, Interim Chief Flood Control Engineer, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Operate in a Fiscally-Responsible and Business-Like Manner.
Pursue County Goals and Objectives by Working with Other Agencies.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). In accordance with the Cooperative Agreement 16-949, Task Force budgets are subject to stakeholder approval. Sufficient appropriation and revenue will be included in the San Bernardino County Flood Control District (District) 2020-21 recommended budget (1990002550-75F01780).

In accordance with Agreement 16-949, approved by the Board of Supervisors (Board) on December 6, 2016 (Item No. 83), the Santa Ana River Watershed Regional Water Quality Standards Task Force (Task Force) has approved the 2020-21 Task Force budget. The District's portion of the budget is funded by the San Bernardino County Areawide Stormwater Program (Program) under Implementation Agreement No. 11-545 (Item No. ...