San Bernardino header
File #: 2322   
Type: Consent Status: Passed
File created: 6/1/2020 Department: Public Works-Transportation
On agenda: 6/9/2020 Final action: 6/9/2020
Subject: Amendment to the Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan Project List
Attachments: 1. ATT-PW-Trans 6-9-20 Amend Measure I Local Street Pass-Thru Funds Five-Year CIP Project List, Road Name List, 2. ATT-PW-Trans 6-9-20 Amend Measure I Local Street Pass-Thru Funds Five-Year CIP Project List, 3. RES-PW-Trans 6-9-20 Amend Measure I Local Street Pass-Thru Funds Five-Year CIP Project List, 4. Item #43 Executed BAI, 5. 2020-96 Executed Resolution
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION

June 9, 2020

FROM
BRENDON BIGGS, Interim Director, Department of Public Works - Transportation

SUBJECT
Title
Amendment to the Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan Project List
End

RECOMMENDATION(S)
Recommendation
Adopt Resolution approving Amendment No. 1 to the County of San Bernardino Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan project list (Attachment A) for 2019-20 through 2023-24 to add projects to the list and modify the scope of certain projects.
(Presenter: Brendon Biggs, Interim Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Pursue County Goals and Objectives by Working with Other Agencies.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Measure "I" Local Street Pass-Through Funds Five-Year Capital Improvement Plan (CIP) project list (Attachment A) identifies projects designated to utilize current and future Measure "I" sales tax revenues. The total estimated cost of projects listed in the amended five-year CIP project list will increase from $31,162,360 to $32,968,325. Sufficient appropriation and revenue for the added and revised projects are included in the Department's 2019-20 Transportation Budget and will be included in future recommended budgets.

BACKGROUND INFORMATION
Pursuant to the Measure "I" program, described below, the Amendment to the County of San Bernardino Measure "I" Local Street Pass-Through Funds Five-Year CIP project list (Attachment A) for 2019-20 through 2023-24 will be submitted to the San Bernardino County Transportation Authority (SBCTA) in order to utilize current and future Measure "I" sales tax revenue for the projects listed.

On November 7, 1989, (Measure "I" 1990-2010 Ordinance No. 89-1) was passed by voters of the ...

Click here for full text