San Bernardino header
File #: 2890   
Type: Consent Status: Passed
File created: 9/8/2020 Department: Assessor/Recorder/County Clerk
On agenda: 9/15/2020 Final action: 9/15/2020
Subject: Contract with Array Information Technology, Inc. to provide System Integration Services for the Assessor's Information Management System Project
Attachments: 1. CON-ARC-9-15-20 Array Information Technology Contract, 2. Item #17 Executed BAI, 3. 20-876 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION

September 15, 2020

FROM
BOB DUTTON, Assessor-Recorder-County Clerk

SUBJECT
Title
Contract with Array Information Technology, Inc. to provide System Integration Services for the Assessor's Information Management System Project
End

RECOMMENDATION(S)
Recommendation
1. Approve a contract with Array Information Technology, Inc. to provide system integration services for the Assessor's Property Information Management System Modernization Project in an amount not to exceed $24,515,030 beginning September 15, 2020 through June 30, 2025.
2. Authorize the Auditor-Controller/Treasurer/Tax Collector to post the necessary budget adjustments to the 2020-21 Budget, as identified in the Financial Impact Section, to establish budget authority for the costs associated with the Assessor's Property Information Management System Modernization Project. (Four Votes Required).
(Presenter: Bob Dutton, Assessor-Recorder-County Clerk, 382-3207)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.
Operate in a Fiscally Responsible and Business-Like Manner.

FINANCIAL IMPACT
Approval of this item will result in the use of additional Discretionary General Funding (Net County Cost). The estimated total cost of the 5-year contract with Array Information Technology, Inc. (Array) is not to exceed $24,515,030 (Contract - $22,925,106; Contingency - $1,589,924).

The estimated implementation cost for the Assessor's Information Management System (AIMS) project is $30.0 million. Implementation costs are to be funded from the New Property Information Management System (PIMS) Replacement Reserve over a five-year period including three years of development and implementation plus two years of post go-live support. Established in 2019-20, the Reserve will be fully funded in 2021-22 after a scheduled $12.5 million contribution. The d...