File #: 4440   
Type: Consent Status: Passed
File created: 6/15/2021 Department: Public Works-Transportation
On agenda: 6/22/2021 Final action: 6/22/2021
Subject: Amendment to Cooperative Agreement with the City of Victorville for the Green Tree Boulevard Extension Project, Victorville Area
Attachments: 1. MAP-PW-Trans 6-22-21 Amend Coop Agr with City of Victorville for Green Tree Blvd Extension Project, 2. AGR-PW-Trans 6-22-21 Amend Coop Agr with City of Victorville for Green Tree Blvd Extension Project, 3. Item #66 Executed BAI, 4. 16-797-A-1 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF THE COUNTY OF SAN BERNARDINO
AND RECORD OF ACTION

June 22, 2021

FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation

SUBJECT
Title
Amendment to Cooperative Agreement with the City of Victorville for the Green Tree Boulevard Extension Project, Victorville Area
End

RECOMMENDATION(S)
Recommendation
Approve Amendment No. 1 to Cooperative Agreement No. 16-797 with the City of Victorville extending the contract termination date from June 30, 2021 to June 30, 2024 for the Green Tree Boulevard Extension Project in the Victorville area.
(Presenter: Brendon Biggs, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Pursue County Goals and Objectives by Working with Other Agencies.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). Amendment No. 1 only extends County Contract No. 16-797 (Agreement) termination date and does not result in any additional financial contribution from the County of San Bernardino (County) for the Green Tree Boulevard Extension Project in the Victorville area (Project).

Under the Agreement the County's fair-share contribution for the Project is $716,901. This amount will be initially funded by a loan of Discretionary General Funds (DGF), approved in the County's 2015-16 Annual Budget in the amount of $841,000. This loan was secured based on a rough Project cost estimate submitted prior to the approval of the Agreement. A loan from the DGF was required because insufficient Development Impact Fees (DIF) have been collected for the County's required DIF contribution. Upon Project completion and receipt of final invoice of the actual Project cost, and sufficient DIF for the Victor Valley Subarea - Arterial account have been collected, the DIF account will reimburse the DGF $841,000 loan for the Project. Sufficient appropriation is included in the Department ...