REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
November 16, 2021
FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation
SUBJECT
Title
Contract with Gentry General Engineering, Inc. for the Laurel Avenue at Randall Avenue Drainage Improvement Project in the Fontana Area
End
RECOMMENDATION(S)
Recommendation
1. Approve Addendum No. 1, issued on September 28, 2021, and Addendum No. 2, issued on October 1, 2021 to the bid documents for the Laurel Avenue at Randall Avenue Drainage Improvement Project in the Fontana Area.
2. Award a construction contract to Gentry General Engineering, Inc. (Rancho Cucamonga, CA) in the amount of $148,029 for the Laurel Avenue at Randall Avenue Drainage Improvement Project in the Fontana Area.
3. Authorize a contingency fund of $14,802 for the Laurel Avenue at Randall Avenue Drainage Improvement Project in the Fontana Area.
4. Authorize the Director of the Department of Public Works to approve the expenditure of the contingency fund of $14,802 for verified quantity overruns for this unit priced construction contract.
5. Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the contract for a total amount not-to-exceed $14,802 of the $14,802 contingency fund, pursuant to Public Contract Code section 20142.
6. Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Brendon Biggs, Director, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Department of Public Works (Department) is funded by Gas Tax r...