San Bernardino header
File #: 5531   
Type: Consent Status: Passed
File created: 2/1/2022 Department: Real Estate Services-Project Management Division
On agenda: 2/8/2022 Final action: 2/8/2022
Subject: Change Order to Construction Contract with McCarthy Building Companies, Inc. for 323 Building Acquisition and Remodel Project for the Public Defender's Office
Attachments: 1. CON-RESD-PM-020822-Change Order for 323 Building Acquisition and Remodel-0114.pdf, 2. Item #51 Executed BAI, 3. 20-89-CO-3 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

February 8, 2022

FROM
TERRY W. THOMPSON, Director, Real Estate Services Department - Project Management

SUBJECT
Title
Change Order to Construction Contract with McCarthy Building Companies, Inc. for 323 Building Acquisition and Remodel Project for the Public Defender's Office
End

RECOMMENDATION(S)
Recommendation
Approve Change Order No. 3 to Contract No. 20-89 with McCarthy Building Companies, Inc. for the 323 Building Acquisition and Remodel Project to be occupied by the Public Defender's Office located at 323 West Court Street in San Bernardino, increasing the total contract amount by $370,056, from $27,110,455 to $27,480,511 (Four votes required).
(Presenter: Terry W. Thompson, Director, 387-5000)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Improve County Government Operations.

FINANCIAL IMPACT
Approval of this item will not result in the use of additional Discretionary General Funding (Net County Cost). The 323 Building Acquisition and Remodel Project (Project) (WBSE 10.10.0114) budget of $37,200,000 has been fully funded with Discretionary General Funding and is comprised of the following components:

Description
Amount
Building Acquisition
$ 2,302,100
Project Management, Inspection
$ 2,570,000
Construction
$25,700,000
Construction Contingency
$ 1,076,589
Add Alternate Allowance
$ 257,100
Honorarium
$ 80,000
Software/Hardware
$ 1,674,800
Furniture, Fixtures and Equipment & Moving Expenses
$ 2,016,000
Construction Cost associated with Amendment No. 1, Change Order No. 1
$ 1,147,364
Change Order No. 2
$5,991
Change Order No. 3
$370,056
Total Project Budget
$37,200,000

There are sufficient funds in the Project's budget to fund the additional cost of Change Order No. 3 to Contract No. 20-89 in the amount of $370,056.

BACKGROUND INFORMATION
The Project, when complete, will result in a new three-story office b...

Click here for full text