REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION
June 14, 2022
FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation
SUBJECT
Title
Contract with S Porter, Inc. for the Baldwin Lane Sidewalk Project in the Big Bear Area
End
RECOMMENDATION(S)
Recommendation
1. Award a construction contract to S. Porter, Inc. (Big Bear Lake, CA) in the amount of $616,415.80 for the Baldwin Lane Sidewalk Project in the Big Bear area.
2. Authorize a contingency fund of $61,641 for the Baldwin Lane Sidewalk Project in the Big Bear area.
3. Authorize the Director of the Department of Public Works to approve the expenditure of the contingency fund of $61,641 for verified quantity overruns for this unit priced construction contract.
4. Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the contract for a total amount not to exceed $43,320 of the $61,641 contingency fund, pursuant to Public Contract Code section 20142.
5. Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Brendon Biggs, Director, 387-7906)
Body
COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.
FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Baldwin Lane Sidewalk Project in the Big Bear area (Project) is funded by Gas Tax revenue and Community Development Block Grant (CDBG) funds. Sufficient appropriation and revenue are included in the Department of Public Works (Department) 2021-22 Road Operations budget and will be included in future recommended budgets (6650002000 20H15029).
BACKGROUND INFORMATION
The Project is located on the north ...