Subject: Contract with Matich Corporation for the Redwood Avenue and Other Roads Project in the Fontana Area
Attachments: 1. MAP-PW-Trans 8-9-22 Con with Matich Corp for Redwood Avenue and Other Roads Project, Fontana Area, 2. CON-PW-Trans 8-9-22 Con with Matich Corp for Redwood Avenue and Other Roads Project, Fontana Area, 3. Item #36 Executed BAI, 4. 22-726 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

August 9, 2022

FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation

SUBJECT
Title
Contract with Matich Corporation for the Redwood Avenue and Other Roads Project in the Fontana Area
End

RECOMMENDATION(S)
Recommendation
1. Award a construction contract to Matich Corporation (San Bernardino, CA) in the amount of $3,094,329 for the Redwood Avenue and Other Roads Project in the Fontana Area.
2. Authorize a contingency fund of $309,432 for the Redwood Avenue and Other Roads Project in the Fontana Area.
3. Authorize the Director of the Department of Public Works to approve the expenditure of the contingency fund of $309,432 for verified quantity overruns for this unit priced construction contract.
4. Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the contract for a total amount not to exceed $167,216 of the $309,432 contingency fund, pursuant to Public Contract Code section 20142.
5. Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Brendon Biggs, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). The Redwood Avenue and Other Roads Project in the Fontana area (Project) is funded by the County's Measure "I" Local Streets Program - San Bernardino Valley Subarea funds. Sufficient appropriation and revenue are included in the Department of Public Works (Department) 2022-23 Measure "I" budget (6650002142 34TX1813).

BACKGROUND INFORMATION
The Project consists of pav...