File #: 6637   
Type: Consent Status: Passed
File created: 9/1/2022 Department: Public Works-Transportation
On agenda: 9/13/2022 Final action: 9/13/2022
Subject: Contract with Matich Corporation for the Wabash Avenue and Other Roads Project in the Redlands, Mentone, and Yucaipa Areas
Attachments: 1. ATT-PW-Trans 9-13-22 Con with Matich Corp. for Wabash Ave and Other Roads Project - Addendum No. 3, 2. ATT-PW-Trans 9-13-22 Con with Matich Corp. for Wabash Ave and Other Roads Project - Addendum No. 4, 3. CON-PW-Trans 9-13-22 Con with Matich Corp. for Wabash Ave and Other Roads Project, 4. MAP-PW-Trans 9-13-22 Con with Matich Corp. for Wabash Ave and Other Roads Project, 5. ATT-PW-Trans 9-13-22 Con with Matich Corp. for Wabash Ave and Other Roads Project - Addendum No. 1, 6. ATT-PW-Trans 9-13-22 Con with Matich Corp. for Wabash Ave and Other Roads Project - Addendum No. 2, 7. Item #50 Executed BAI, 8. 22-796 Executed Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

September 13, 2022

FROM
BRENDON BIGGS, Director, Department of Public Works - Transportation

SUBJECT
Title
Contract with Matich Corporation for the Wabash Avenue and Other Roads Project in the Redlands, Mentone, and Yucaipa Areas
End

RECOMMENDATION(S)
Recommendation
1. Approve Addendum No. 1, issued on August 4, 2022, Addendum No. 2, issued on August 10, 2022, Addendum No. 3, issued on August 11, 2022, and Addendum No. 4, issued on August 12, 2022 to the bid documents for the Wabash Avenue and Other Roads Project in the Redlands, Mentone, and Yucaipa areas.
2. Award a construction contract to Matich Corporation (San Bernardino, CA) in the amount of $3,336,334 for the Wabash Avenue and Other Roads Project in the Redlands, Mentone, and Yucaipa areas.
3. Authorize a contingency fund of $333,633 for the Wabash Avenue and Other Roads Project in the Redlands, Mentone, and Yucaipa areas.
4. Authorize the Director of the Department of Public Works to approve the expenditure of the contingency fund of $333,633 for verified quantity overruns for this unit priced construction contract.
5. Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the contract for a total amount not to exceed $179,316 of the $333,633 contingency fund, pursuant to Public Contract Code section 20142.
6. Authorize the Director of the Department of Public Works to accept the work when 100% complete and execute and file the Notice of Completion.
(Presenter: Brendon Biggs, Director, 387-7906)
Body

COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES
Ensure Development of a Well-Planned, Balanced, and Sustainable County.
Provide for the Safety, Health and Social Service Needs of County Residents.

FINANCIAL IMPACT
Approval of this item will not result in the use of Discretionary General Funding (Net County Cost). Th...