Subject: Contract with Sukut Construction, LLC for the Final Closure Construction Project at the Colton Sanitary Landfill
Attachments: 1. ATT-PW-Waste 9-13-22 Con with Sukut Construction for Final Closure Project at Colton Landfill - Addendum 4, 2. ATT-PW-Waste 9-13-22 Con with Sukut Construction for Final Closure Project at Colton Landfill - Addendum 5, 3. ATT-PW-Waste 9-13-22 Con with Sukut Construction for Final Closure Project at Colton Landfill - Addendum 6, 4. CON-PW-Waste 9-13-22 Con with Sukut Construction for Final Closure Project at Colton Landfill, 5. MAP-PW-Waste 9-13-22 Con with Sukut Construction for Final Closure Project at Colton Landfill, 6. ATT-PW-Waste 9-13-22 Con with Sukut Construction for Final Closure Project at Colton Landfill - Addendum 1, 7. ATT-PW-Waste 9-13-22 Con with Sukut Construction for Final Closure Project at Colton Landfill - Addendum 2, 8. ATT-PW-Waste 9-13-22 Con with Sukut Construction for Final Closure Project at Colton Landfill - Addendum 3, 9. ADD-COV-PW-Waste 9-13-22 Con with Sukut Construction for Final Closure Project at Colton Landfill - Escrow Agr, 10. ADD-AGR-PW-Waste 9-13-22 Con with Sukut Construction for Final Closure Project at Colton Landfill - Escrow, 11. Item #47 Executed BAI, 12. 22-811 Executed Contract, 13. 22-812 Unexecuted Contract
REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS
OF SAN BERNARDINO COUNTY
AND RECORD OF ACTION

September 13, 2022

FROM
BRENDON BIGGS, Director, Department of Public Works - Solid Waste Management

SUBJECT
Title
Contract with Sukut Construction, LLC for the Final Closure Construction Project at the Colton Sanitary Landfill
End

RECOMMENDATION(S)
Recommendation
1. Approve Addendum No. 1, issued on May 19, 2022, Addendum No. 2, issued on June 9, 2022, Addendum No. 3, issued on June 13, 2022, Addendum No. 4, issued on June 16, 2022, Addendum No. 5, issued on June 22, 2022, and Addendum No. 6, issued on June 28, 2022, to the bid documents for the Final Closure Construction Project at the Colton Sanitary Landfill.
2. Award a construction contract to Sukut Construction, LLC (Santa Ana, California) in the amount of $35,667,093 for the Final Closure Construction Project at the Colton Sanitary Landfill.
3. Authorize a contingency fund of $3,566,709 for the Final Closure Construction Project at the Colton Sanitary Landfill.
4. Authorize the Director of the Department of Public Works to approve the expenditure of the contingency fund of $3,566,709 for verified quantity overruns for this unit priced construction contract.
5. Authorize the Director of the Department of Public Works to order any necessary changes or additions in the work being performed under the contract for a total amount not to exceed $210,000 of the $3,566,709 contingency fund, pursuant to Public Contract Code section 20142.
6. Approve Escrow Agreement for Security Deposits in Lieu of Retention with Sukut Construction, LLC and Banner Bank pursuant to Public Contract Code section 22300 for the Final Closure Construction Project at the Colton Sanitary Landfill.
7. Authorize the Director of the Department of Public Works to execute the Escrow Agreement and to provide and receive written notice under the agreement for the Final Closure Construction Project at the Colton Sanitary Landfill.
8. Direct the D...